3720 S BARBARA ST 90731

Certificate Information: 3720 S BARBARA ST 90731

Application / Permit
21014-10000-04669
Plan Check / Job No.
B21LA17270
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ONE STORY GROUND FLOOR ADDITION AT REAR FOR NEW MASTER BED AND BATH.
Permit Issued
Issued on 2/24/2022
Issuing Office
Current Status
CofO Issued on 8/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/15/2021 APPLICANT
Assigned to Plan Check Engineer 9/17/2021 JOE VO
Corrections Issued 9/17/2021 JOE VO
Applicant returned to address corrections 11/18/2021 SELLA BENYAMIN
Applicant returned to address corrections 12/7/2021 JOE VO
Applicant returned to address corrections 2/16/2022 JOE VO
Plan Check Approved 2/16/2022 JOE VO
Issued 2/24/2022 APPLICANT
CofO in Progress 8/8/2023 JOHN KLARIN
Permit Finaled 8/8/2023 ANSON MAGLASANG
CofO Issued 8/8/2023 ANSON MAGLASANG
Permit Finaled 8/8/2023 ANSON MAGLASANG

Permit Application Clearance Information

Coastal Zone Cleared 2/8/2022 LAUREN PADICK
Specific Plan Cleared 2/9/2022 DAISY BENICIA
Eng Process Fee Ord 176,300 Cleared 2/18/2022 ANA VILLA
Roof/Waste drainage to street Cleared 2/18/2022 ANA VILLA
Sewer availability Cleared 2/18/2022 ANA VILLA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/23/2022 Corrections Issued ANSON MAGLASANG
Footing/Foundation/Slab 3/31/2022 Approved ANSON MAGLASANG
BUILDING-Rough-Frame 5/2/2022 Partial Approval ANSON MAGLASANG
Green Building Rough 5/2/2022 Not Ready for Inspection ANSON MAGLASANG
Deputy Wood Construction 6/16/2022 Conditional Approval ANSON MAGLASANG
BUILDING-Rough-Frame 6/23/2022 Not Ready for Inspection ANSON MAGLASANG
ELECTRICAL-Rough 6/23/2022 Not Ready for Inspection ANSON MAGLASANG
Green Building Rough 6/23/2022 Not Ready for Inspection ANSON MAGLASANG
PLUMBING-Rough 6/23/2022 Not Ready for Inspection ANSON MAGLASANG
BUILDING-Rough-Frame 7/13/2022 Corrections Issued ANSON MAGLASANG
Green Building Rough 7/13/2022 Not Ready for Inspection ANSON MAGLASANG
ELECTRICAL-Rough 7/14/2022 Approved ANSON MAGLASANG
Insulation 7/14/2022 Approved ANSON MAGLASANG
PLUMBING-Rough 7/14/2022 Approved ANSON MAGLASANG
Drywall Nailing 7/26/2022 Approved ANSON MAGLASANG
Green Building Rough 7/26/2022 Approved ANSON MAGLASANG
Interior/Exterior Lathing 7/26/2022 Partial Approval ANSON MAGLASANG
Shower Pan 8/3/2022 Approved ANSON MAGLASANG
Interior/Exterior Lathing 8/11/2022 Partial Approval ANSON MAGLASANG
Pre-Inspection 8/15/2022 Approved ANSON MAGLASANG
BUILDING-Rough-Frame 1/25/2023 Approved JOHN KLARIN
Final 1/25/2023 Corrections Issued JOHN KLARIN
Green Building Final 1/25/2023 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 1/25/2023 SGSOV Approved JOHN KLARIN
Smoke Detectors 1/25/2023 Approved JOHN KLARIN
Final 6/2/2023 Corrections Issued ANSON MAGLASANG
Final 7/24/2023 Not Ready for Inspection JOHN KLARIN
Final 7/31/2023 Not Ready for Inspection JOHN KLARIN
Final 8/7/2023 OK to Issue CofO JOHN KLARIN