510 N NEVA PL 90042

Certificate Information: 510 N NEVA PL 90042

Application / Permit
21014-10000-04666
Plan Check / Job No.
B21LA17255
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT PORTION OF (E) DETACHED GARAGE (312 SQ FT) AND SECOND FLOOR ADDITION (407 SQ FT) IN TO A (N) ADU (716 SQ FT); 1 CAR GARAGE (164 SQ FT) TO REMAIN PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 9/30/2022
Issuing Office
Metro
Current Status
CofO Issued on 2/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/16/2021 APPLICANT
Assigned to Plan Check Engineer 9/17/2021 SINA KHOSRAVI
Corrections Issued 9/19/2021 SINA KHOSRAVI
Building Plans Picked Up 10/26/2021 APPLICANT
Applicant returned to address corrections 8/4/2022 KHUONG TRUONG
Applicant returned to address corrections 8/22/2022 JOSEPH RAFOLS
Applicant returned to address corrections 9/16/2022 LUKE GONZALES
Plan Check Approved 9/30/2022 FERNANDO FLORES
Issued 9/30/2022 APPLICANT
CofO in Progress 2/12/2025 CRAIG DAVIS
Permit Finaled 2/23/2025 DEROLD HAUFF
CofO Issued 2/23/2025 DEROLD HAUFF
Permit Finaled 2/23/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/10/2022 CELINA MORENO
Roof/Waste drainage to street Cleared 6/10/2022 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 6/14/2022 CINDY QI
Sewer availability Cleared 6/14/2022 CINDY QI
Grading Pre-Inspection Cleared 6/28/2022 KIRK LINKLATER

Contact Information

Contractor Owner-Builder       ,
Engineer Adams,, Robert Charles; Lic. No.: C21234 22129 BRYANT STREET      CANOGA PARK, CA 91304

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/4/2022 Partial Approval CRAIG VAUGHAN
Deputy Drilled-In Anchors 8/21/2024 Conditional Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 8/23/2024 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 8/23/2024 Partial Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 9/11/2024 Partial Approval ALIZAH MAYAGOITIA
Deputy Wood Construction 10/4/2024 Conditional Approval ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 10/8/2024 Partial Approval ALIZAH MAYAGOITIA
Gas Test 10/8/2024 Partial Approval ALIZAH MAYAGOITIA
HVAC-Rough 10/8/2024 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 10/8/2024 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 10/15/2024 Corrections Issued ALIZAH MAYAGOITIA
ELECTRICAL-Rough 10/15/2024 Approved ALIZAH MAYAGOITIA
Green Building Rough 10/15/2024 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 10/15/2024 Partial Approval ALIZAH MAYAGOITIA
Insulation 10/28/2024 Partial Approval ALIZAH MAYAGOITIA
Interior/Exterior Lathing 10/28/2024 Partial Approval ALIZAH MAYAGOITIA
Shower Pan 10/28/2024 Approved ALIZAH MAYAGOITIA
Insulation 10/29/2024 Approved ANTHONY RAMOS
Drywall Nailing 10/31/2024 Approved ROY SPAULDING
Interior/Exterior Lathing 10/31/2024 Approved ROY SPAULDING
ELECTRICAL-Rough 1/10/2025 Approved OSVALDO PARAMO
HVAC-Rough 1/10/2025 Approved OSVALDO PARAMO
PLUMBING-Rough 1/10/2025 Approved OSVALDO PARAMO
Underground Mechanical 1/10/2025 Approved OSVALDO PARAMO
Service/Power Release 1/16/2025 Partial Inspection CRAIG DAVIS
ELECTRICAL-Final 1/17/2025 Corrections Issued CRAIG DAVIS
HVAC-Final 1/17/2025 Corrections Issued CRAIG DAVIS
PLUMBING-Final 1/17/2025 Corrections Issued CRAIG DAVIS
BUILDING-Rough-Frame 1/21/2025 Not Ready for Inspection CRAIG DAVIS
ELECTRICAL-Final 1/21/2025 Not Ready for Inspection CRAIG DAVIS
Final 1/21/2025 Not Ready for Inspection CRAIG DAVIS
Green Building Final 1/21/2025 Corrections Issued CRAIG DAVIS
HVAC-Final 1/21/2025 Not Ready for Inspection CRAIG DAVIS
PLUMBING-Final 1/21/2025 Not Ready for Inspection CRAIG DAVIS
SGSOV-Seismic Gas S/O Valve 1/21/2025 SGSOV Not Ready CRAIG DAVIS
Smoke Detectors 1/21/2025 Not Ready for Inspection CRAIG DAVIS
ELECTRICAL-Final 1/24/2025 Approved THOMAS LOGRASSO
Final 1/24/2025 Corrections Issued THOMAS LOGRASSO
PLUMBING-Final 1/24/2025 Approved THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 1/24/2025 SGSOV Approved THOMAS LOGRASSO
Smoke Detectors 1/24/2025 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 1/31/2025 Approved ALIZAH MAYAGOITIA
Final 1/31/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Green Building Final 1/31/2025 Approved ALIZAH MAYAGOITIA
Final 2/5/2025 Not Ready for Inspection CRAIG DAVIS
Final 2/10/2025 Conditional Approval BRENDAN MORELLI
Service/Power Release 2/10/2025 Approved BRENDAN MORELLI
Final 2/12/2025 OK to Issue CofO CRAIG DAVIS
HVAC-Final 2/12/2025 Approved CRAIG DAVIS