1531 1/2 W 53RD ST 90062

Certificate Information: 1531 1/2 W 53RD ST 90062

Application / Permit
21014-10000-04632
Plan Check / Job No.
B21LA17124
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) detached two-car garage to Accessory Dwelling Unit per Ordinance with one-story addition to ADU. All work per WFPP.
Permit Issued
Issued on 4/14/2022
Issuing Office
Current Status
CofO Issued on 10/8/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/13/2021 APPLICANT
Assigned to Plan Check Engineer 9/16/2021 SAMUEL GONZALEZ
Corrections Issued 9/21/2021 SAMUEL GONZALEZ
Applicant returned to address corrections 2/3/2022 DANIEL SANJUAN
Issued 4/14/2022 APPLICANT
Building Plans Picked Up 4/22/2022 APPLICANT
CofO in Progress 9/29/2022 STUART CHAPMAN
Permit Finaled 10/8/2022 DEROLD HAUFF
CofO Issued 10/8/2022 DEROLD HAUFF
Permit Finaled 10/8/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/20/2021 WALLIE JONG
Roof/Waste drainage to street Cleared 12/20/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 12/27/2021 WALLIE JONG
Sewer availability Cleared 12/27/2021 WALLIE JONG
Community Plan Implem. Overlay Cleared 1/6/2022 RAFAEL FONTES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/13/2022 Not Ready for Inspection SABAS ALONSO
Footing/Foundation/Slab 5/18/2022 Approved SABAS ALONSO
BUILDING-Rough-Frame 6/15/2022 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 6/15/2022 Approved SABAS ALONSO
PLUMBING-Rough 6/15/2022 Corrections Issued SABAS ALONSO
BUILDING-Rough-Frame 6/24/2022 Approved SABAS ALONSO
Green Building Rough 6/24/2022 Approved SABAS ALONSO
PLUMBING-Rough 6/24/2022 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 6/30/2022 Approved SABAS ALONSO
Insulation 6/30/2022 Approved SABAS ALONSO
Interior/Exterior Lathing 6/30/2022 Partial Approval SABAS ALONSO
Drywall Nailing 7/6/2022 Corrections Issued SABAS ALONSO
Pre-Inspection 7/12/2022 Partial Approval SABAS ALONSO
Drywall Nailing 8/19/2022 Approved HORACE FULTZ
Final 8/19/2022 Corrections Issued HORACE FULTZ
SGSOV-Seismic Gas S/O Valve 8/19/2022 SGSOV Not Ready HORACE FULTZ
Smoke Detectors 8/19/2022 Partial Approval HORACE FULTZ
Final 8/23/2022 Corrections Issued ENRIQUE MIRELES
Final 8/26/2022 Corrections Issued STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 8/26/2022 SGSOV Approved STUART CHAPMAN
Service/Power Release 8/26/2022 Approved STUART CHAPMAN
Smoke Detectors 8/26/2022 Approved STUART CHAPMAN
ELECTRICAL-Final 9/29/2022 Approved STUART CHAPMAN
Final 9/29/2022 OK to Issue CofO STUART CHAPMAN
HVAC-Final 9/29/2022 Approved STUART CHAPMAN
PLUMBING-Final 9/29/2022 Approved STUART CHAPMAN
Service/Power Release 9/29/2022 Approved STUART CHAPMAN
Service/Power Release 9/29/2022 Not Ready for Inspection STUART CHAPMAN