9400 S HOBART BLVD 90047

Certificate Information: 9400 S HOBART BLVD 90047

Application / Permit
21014-10000-04627
Plan Check / Job No.
B21LA17099
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW GROUND FLOOR ADDITION TO (E) ONE STORY SINGLE FAMILY DWELLING.
Permit Issued
Issued on 1/11/2023
Issuing Office
Metro
Current Status
CofO Issued on 12/26/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/13/2021 APPLICANT
Assigned to Plan Check Engineer 10/14/2021 GARO TELMI
Corrections Issued 10/29/2021 GARO TELMI
Quality Review Completed 11/4/2021 KEN GILL
Building Plans Picked Up 1/3/2022 APPLICANT
Applicant returned to address corrections 6/13/2022 GARO TELMI
Applicant returned to address corrections 9/27/2022 GARO TELMI
Applicant returned to address corrections 12/6/2022 GARO TELMI
Applicant returned to address corrections 12/27/2022 GARO TELMI
Plan Check Approved 1/11/2023 GARO TELMI
Issued 1/11/2023 APPLICANT
CofO in Progress 12/13/2024 JOSE MACIAS
Permit Finaled 12/26/2024 DEROLD HAUFF
CofO Issued 12/26/2024 DEROLD HAUFF
Permit Finaled 12/26/2024 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/6/2022 AMAAN MALIK
Roof/Waste drainage to street Cleared 11/3/2022 AMAAN MALIK

Contact Information

Contractor Owner-Builder       ,
Engineer Martirossyan,, Armen; Lic. No.: C64223 802 PORTOLA AVE      GLENDALE, CA 91206

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/5/2023 Corrections Issued ENRIQUE MIRELES
Excavation/Setback/Form/Re-Bar 12/13/2023 Approved ENRIQUE MIRELES
PLUMBING-Rough 1/2/2024 Approved ENRIQUE MIRELES
PLUMBING-Rough 1/4/2024 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 1/17/2024 Partial Approval MICHAEL LEWIS
BUILDING-Rough-Frame 2/8/2024 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 2/8/2024 Approved ENRIQUE MIRELES
METHANE-Barrier 2/8/2024 Approved ENRIQUE MIRELES
METHANE-Rough 2/8/2024 Approved ENRIQUE MIRELES
METHANE-Subgrade 2/8/2024 Approved ENRIQUE MIRELES
Wood Frame 3/14/2024 Approved JOSE MACIAS
BUILDING-Rough-Frame 4/2/2024 Not Ready for Inspection ANTHONY EGSON
Green Building Rough 4/2/2024 Not Ready for Inspection ANTHONY EGSON
Wood Frame 4/4/2024 Corrections Issued JOSE MACIAS
Wood Frame 4/12/2024 Corrections Issued JOSE MACIAS
Insulation 5/1/2024 Approved MICHAEL LEWIS
Wood Frame 5/6/2024 Approved JOSE MACIAS
Shower Pan 6/3/2024 No Access for Inspection JOSE MACIAS
Floor/Roof Diaphrgm/Shear Wall 6/5/2024 Approved JOSE MACIAS
BUILDING-Rough-Frame 10/4/2024 Approved LUIS CASTRO
Final 10/4/2024 Corrections Issued LUIS CASTRO
Green Building Final 10/4/2024 Approved LUIS CASTRO
Green Building Rough 10/4/2024 Approved LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 10/4/2024 SGSOV Not Ready LUIS CASTRO
Smoke Detectors 10/4/2024 Approved LUIS CASTRO
Final 10/22/2024 Corrections Issued JOSE MACIAS
SGSOV-Seismic Gas S/O Valve 10/22/2024 SGSOV Approved JOSE MACIAS
Final 12/9/2024 Conditional Approval JOSE MACIAS
Final 12/12/2024 OK to Issue CofO JOSE MACIAS