13251 W RAVEN ST 91342
Certificate Information: 13251 W RAVEN ST 91342
- Application / Permit
- 21014-10000-04623
- Plan Check / Job No.
- B21LA17076
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO EXISTING 1-STORY SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 7/22/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/30/2021 | ERIC WONG |
| Corrections Issued | 10/3/2021 | ERIC WONG |
| Quality Review Completed | 10/7/2021 | PETER KIM |
| Building Plans Picked Up | 10/19/2021 | APPLICANT |
| Applicant returned to address corrections | 10/21/2021 | ERIC WONG |
| Applicant returned to address corrections | 4/29/2022 | ERIC WONG |
| Plan Check Approved | 7/22/2022 | ERIC WONG |
| Issued | 7/22/2022 | APPLICANT |
| CofO in Progress | 9/20/2023 | KEVIN BERBERYAN |
| Permit Finaled | 10/24/2023 | RUBEN SALAS |
| CofO Issued | 10/24/2023 | RUBEN SALAS |
| Permit Finaled | 10/24/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/16/2021 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 12/28/2021 | BRIAN MILLER |
| Low Impact Development | Cleared | 3/29/2022 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 4/4/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 5/9/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 6/6/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zelada,, Mynor Anibal; Lic. No.: C48666 | 22634 SYLVAN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/3/2022 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 10/21/2022 | Partial Approval | ARAM AVEDISIAN |
| Insulation | 10/21/2022 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 10/21/2022 | Partial Approval | ARAM AVEDISIAN |
| Sewer | 10/28/2022 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 12/30/2022 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 12/30/2022 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 12/30/2022 | Not Ready for Inspection | ARAM AVEDISIAN |
| HVAC-Rough | 12/30/2022 | Not Ready for Inspection | ARAM AVEDISIAN |
| PLUMBING-Rough | 12/30/2022 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 1/13/2023 | Corrections Issued | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 2/1/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 2/1/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 2/1/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 2/1/2023 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 2/14/2023 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 2/14/2023 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 2/14/2023 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 2/14/2023 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 3/21/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 4/19/2023 | Approved | ARAM AVEDISIAN |
| Insulation | 4/19/2023 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 4/27/2023 | Approved | ARAM AVEDISIAN |
| Final | 6/26/2023 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 6/26/2023 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 6/26/2023 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 6/26/2023 | Not Ready for Inspection | ARAM AVEDISIAN |
| Final | 8/28/2023 | Not Ready for Inspection | ROBERT GOLD |
| Smoke Detectors | 8/28/2023 | Approved | ROBERT GOLD |
| Final | 9/19/2023 | OK to Issue CofO | KEVIN BERBERYAN |
| Service/Power Release | 10/12/2023 | Approved | KEVIN BERBERYAN |