1218 W BIG CANYON PL 90732
Certificate Information: 1218 W BIG CANYON PL 90732
- Application / Permit
- 21014-10000-04594
- Plan Check / Job No.
- B21LA16922
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *ePlan Check* PROPOSED ADDITION TO (E) SFD
- Permit Issued
- Issued on 6/22/2022
- Issuing Office
- Current Status
- CofO Issued on 2/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/4/2021 | CRYSTEL MAALOUF |
| Corrections Issued | 11/12/2021 | CRYSTEL MAALOUF |
| Quality Review Completed | 11/16/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 1/4/2022 | CRYSTEL MAALOUF |
| Plan Check Approved | 4/11/2022 | CRYSTEL MAALOUF |
| Issued | 6/22/2022 | APPLICANT |
| CofO in Progress | 2/12/2024 | JAMES CHAVEZ |
| Permit Finaled | 2/12/2024 | ANSON MAGLASANG |
| CofO Issued | 2/12/2024 | ANSON MAGLASANG |
| Permit Finaled | 2/12/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 3/2/2022 | HUGO LOPEZ |
| GPI Written Notices | Cleared | 3/9/2022 | CRYSTEL MAALOUF |
| Grading Pre-Inspection | Cleared | 3/9/2022 | SERGIO VALENZUELA |
| Sewer availability | Cleared | 3/29/2022 | JOSE HERNANDEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hale,, Ronald Richard; Lic. No.: C17056 | 1869 PALACIOS DR SAN PEDRO, CA 90732 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/23/2022 | Partial Inspection | ANSON MAGLASANG |
| Deputy Drilled-In Anchors | 2/14/2023 | Conditional Approval | ANSON MAGLASANG |
| Excavation/Setback/Form/Re-Bar | 2/22/2023 | Approved | EUGENE CASSIDY |
| Deputy Reinf. Concrete | 2/23/2023 | Conditional Approval | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 5/19/2023 | Not Ready for Inspection | ANSON MAGLASANG |
| Green Building Rough | 5/19/2023 | Not Ready for Inspection | ANSON MAGLASANG |
| Wood Frame | 5/19/2023 | Not Ready for Inspection | ANSON MAGLASANG |
| BUILDING-Rough-Frame | 5/31/2023 | Partial Approval | JOHN KLARIN |
| Green Building Rough | 5/31/2023 | Not Ready for Inspection | JOHN KLARIN |
| ELECTRICAL-Rough | 7/24/2023 | Approved | JAMES CHAVEZ |
| PLUMBING-Rough | 7/24/2023 | Approved | JAMES CHAVEZ |
| HVAC-Rough | 8/2/2023 | Approved | ANSON MAGLASANG |
| Insulation | 8/2/2023 | Approved | ANSON MAGLASANG |
| Drywall Nailing | 8/16/2023 | Approved | JAMES CHAVEZ |
| Interior/Exterior Lathing | 8/16/2023 | Partial Approval | JAMES CHAVEZ |
| Shower Pan | 8/22/2023 | Approved | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 11/30/2023 | Approved | ANSON MAGLASANG |
| Final | 11/30/2023 | Not Ready for Inspection | ANSON MAGLASANG |
| Footing/Foundation/Slab | 11/30/2023 | Approved | ANSON MAGLASANG |
| Green Building Final | 11/30/2023 | Approved | ANSON MAGLASANG |
| Green Building Rough | 11/30/2023 | Approved | ANSON MAGLASANG |
| SGSOV-Seismic Gas S/O Valve | 11/30/2023 | SGSOV Approved | ANSON MAGLASANG |
| Smoke Detectors | 11/30/2023 | Approved | ANSON MAGLASANG |
| Final | 2/2/2024 | OK to Issue CofO | JAMES CHAVEZ |