1218 W BIG CANYON PL 90732

Certificate Information: 1218 W BIG CANYON PL 90732

Application / Permit
21014-10000-04594
Plan Check / Job No.
B21LA16922
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
*ePlan Check* PROPOSED ADDITION TO (E) SFD
Permit Issued
Issued on 6/22/2022
Issuing Office
Current Status
CofO Issued on 2/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/5/2021 APPLICANT
Assigned to Plan Check Engineer 11/4/2021 CRYSTEL MAALOUF
Corrections Issued 11/12/2021 CRYSTEL MAALOUF
Quality Review Completed 11/16/2021 HERNAN ARREOLA
Applicant returned to address corrections 1/4/2022 CRYSTEL MAALOUF
Plan Check Approved 4/11/2022 CRYSTEL MAALOUF
Issued 6/22/2022 APPLICANT
CofO in Progress 2/12/2024 JAMES CHAVEZ
Permit Finaled 2/12/2024 ANSON MAGLASANG
CofO Issued 2/12/2024 ANSON MAGLASANG
Permit Finaled 2/12/2024 ANSON MAGLASANG

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/2/2022 HUGO LOPEZ
GPI Written Notices Cleared 3/9/2022 CRYSTEL MAALOUF
Grading Pre-Inspection Cleared 3/9/2022 SERGIO VALENZUELA
Sewer availability Cleared 3/29/2022 JOSE HERNANDEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Hale,, Ronald Richard; Lic. No.: C17056 1869 PALACIOS DR      SAN PEDRO, CA 90732

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/23/2022 Partial Inspection ANSON MAGLASANG
Deputy Drilled-In Anchors 2/14/2023 Conditional Approval ANSON MAGLASANG
Excavation/Setback/Form/Re-Bar 2/22/2023 Approved EUGENE CASSIDY
Deputy Reinf. Concrete 2/23/2023 Conditional Approval JAMES CHAVEZ
BUILDING-Rough-Frame 5/19/2023 Not Ready for Inspection ANSON MAGLASANG
Green Building Rough 5/19/2023 Not Ready for Inspection ANSON MAGLASANG
Wood Frame 5/19/2023 Not Ready for Inspection ANSON MAGLASANG
BUILDING-Rough-Frame 5/31/2023 Partial Approval JOHN KLARIN
Green Building Rough 5/31/2023 Not Ready for Inspection JOHN KLARIN
ELECTRICAL-Rough 7/24/2023 Approved JAMES CHAVEZ
PLUMBING-Rough 7/24/2023 Approved JAMES CHAVEZ
HVAC-Rough 8/2/2023 Approved ANSON MAGLASANG
Insulation 8/2/2023 Approved ANSON MAGLASANG
Drywall Nailing 8/16/2023 Approved JAMES CHAVEZ
Interior/Exterior Lathing 8/16/2023 Partial Approval JAMES CHAVEZ
Shower Pan 8/22/2023 Approved JAMES CHAVEZ
BUILDING-Rough-Frame 11/30/2023 Approved ANSON MAGLASANG
Final 11/30/2023 Not Ready for Inspection ANSON MAGLASANG
Footing/Foundation/Slab 11/30/2023 Approved ANSON MAGLASANG
Green Building Final 11/30/2023 Approved ANSON MAGLASANG
Green Building Rough 11/30/2023 Approved ANSON MAGLASANG
SGSOV-Seismic Gas S/O Valve 11/30/2023 SGSOV Approved ANSON MAGLASANG
Smoke Detectors 11/30/2023 Approved ANSON MAGLASANG
Final 2/2/2024 OK to Issue CofO JAMES CHAVEZ