2982 N TIFFANY CIR 90077

Certificate Information: 2982 N TIFFANY CIR 90077

Application / Permit
21014-10000-04584
Plan Check / Job No.
B21LA16860
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERSION OF EXISTING GARAGE INTO BEDROOM AND LAUNDRY. ADD NEW TWO CAR GARAGE TO FRONT OF DWELLING.
Permit Issued
Issued on 12/17/2021
Issuing Office
Current Status
CofO Issued on 1/19/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/9/2021 APPLICANT
Assigned to Plan Check Engineer 9/13/2021 RICARDO RAMIREZ
Corrections Issued 9/13/2021 RICARDO RAMIREZ
Building Plans Picked Up 9/14/2021 APPLICANT
Plan Check Approved 12/17/2021 DANIEL SANJUAN
Issued 12/17/2021 APPLICANT
CofO in Progress 7/20/2022 MICHAEL PELHAM
No Progress 1/14/2023 MICHAEL PELHAM
CofO in Progress 1/14/2023 MICHAEL PELHAM
Permit Finaled 1/19/2023 DANIEL ORRANTE
CofO Issued 1/19/2023 DANIEL ORRANTE
Permit Finaled 1/19/2023 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/16/2021 CATHERINE ADROVER
Sewer availability Cleared 9/16/2021 CATHERINE ADROVER
Eng Process Fee Ord 176,300 Cleared 9/20/2021 CATHERINE ADROVER
Specific Plan Cleared 11/4/2021 OLGA AYALA
ZI Cleared 11/4/2021 OLGA AYALA
Hydrant and Access approval Cleared 11/30/2021 GREGORY HOERNER
Grading Pre-Inspection Cleared 12/16/2021 RICARDO RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Tabirara,, Vernon Nicolas; Lic. No.: C75492 17520 DAPHNE AVE      TORRANCE, CA 90504

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/22/2021 Approved GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 1/4/2022 Corrections Issued BRENDAN LOONEY
Excavation/Setback/Form/Re-Bar 1/24/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 1/24/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 2/7/2022 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 2/7/2022 Approved GERMAN RODRIGUEZ MENDOZA
Green Building Rough 2/7/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Drywall Nailing 3/7/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 3/7/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Shower Pan 3/7/2022 Approved GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 3/18/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 3/18/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 3/18/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 3/18/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Special/Order Compliance 3/18/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 3/24/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 3/24/2022 Approved GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 3/24/2022 Approved GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 3/24/2022 Approved GERMAN RODRIGUEZ MENDOZA
Drywall Nailing 4/4/2022 Approved GERMAN RODRIGUEZ MENDOZA
Insulation 4/4/2022 Approved GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 6/30/2022 Approved MICHAEL PELHAM
ELECTRICAL-Final 6/30/2022 Corrections Issued MICHAEL PELHAM
Final 6/30/2022 Corrections Issued MICHAEL PELHAM
Green Building Final 6/30/2022 Approved MICHAEL PELHAM
Green Building Rough 6/30/2022 Approved MICHAEL PELHAM
HVAC-Final 6/30/2022 Approved MICHAEL PELHAM
PLUMBING-Final 6/30/2022 Approved MICHAEL PELHAM
SGSOV-Seismic Gas S/O Valve 6/30/2022 SGSOV Approved MICHAEL PELHAM
Smoke Detectors 6/30/2022 Corrections Issued MICHAEL PELHAM
ELECTRICAL-Final 7/19/2022 Approved MICHAEL PELHAM
Final 7/19/2022 OK to Issue CofO MICHAEL PELHAM
Smoke Detectors 7/19/2022 Approved MICHAEL PELHAM