139 1/4 E 88TH ST 90003
Certificate Information: 139 1/4 E 88TH ST 90003
- Application / Permit
- 21014-10000-04577
- Plan Check / Job No.
- B21LA16841
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) detached one-car garage (12' x 16') to Accessory Dwelling Unit per Ordinance with one-story addition to ADU. All work per engineered design.
- Permit Issued
- Issued on 12/7/2021
- Issuing Office
- Current Status
- CofO Issued on 11/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/14/2021 | LUKE GONZALES |
| Corrections Issued | 9/14/2021 | LUKE GONZALES |
| Applicant returned to address corrections | 11/18/2021 | LUKE GONZALES |
| Building Plans Picked Up | 11/23/2021 | APPLICANT |
| Issued | 12/7/2021 | APPLICANT |
| CofO in Progress | 10/13/2023 | MICHAEL LEWIS |
| CofO Issued | 11/7/2023 | DEROLD HAUFF |
| Permit Finaled | 11/7/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 9/19/2021 | THOMAS LANG |
| Roof/Waste drainage to street | Cleared | 9/19/2021 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 9/21/2021 | THOMAS LANG |
| Sewer availability | Cleared | 9/27/2021 | THOMAS LANG |
Contact Information
| Contractor | Jerahian Araz; Lic. No.: 1045340-B | 250 N COLLEGE PARK DR F36 UPLAND, CA 91786 |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/12/2022 | Partial Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 9/12/2022 | Conditional Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 10/6/2022 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 10/24/2022 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 11/23/2022 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2022 | Approved | LILIANA PORTILLO |
| Deputy Wood Construction | 12/20/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 1/23/2023 | Corrections Issued | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2023 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 1/23/2023 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 1/23/2023 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 1/30/2023 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 1/30/2023 | Approved | LILIANA PORTILLO |
| Sewer | 1/30/2023 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 2/1/2023 | Approved | LILIANA PORTILLO |
| Green Building Rough | 2/1/2023 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 2/1/2023 | Partial Approval | LILIANA PORTILLO |
| Insulation | 2/28/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 2/28/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Shower Pan | 2/28/2023 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 3/3/2023 | Approved | ALIZAH MAYAGOITIA |
| Final | 6/7/2023 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 6/7/2023 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 6/7/2023 | SGSOV Approved | STUART CHAPMAN |
| Smoke Detectors | 6/7/2023 | Approved | STUART CHAPMAN |
| Final | 9/12/2023 | Conditional Approval | MICHAEL LEWIS |
| Final | 10/2/2023 | Corrections Issued | MICHAEL LEWIS |
| Final | 10/12/2023 | OK to Issue CofO | MICHAEL LEWIS |