139 1/4 E 88TH ST 90003

Certificate Information: 139 1/4 E 88TH ST 90003

Application / Permit
21014-10000-04577
Plan Check / Job No.
B21LA16841
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) detached one-car garage (12' x 16') to Accessory Dwelling Unit per Ordinance with one-story addition to ADU. All work per engineered design.
Permit Issued
Issued on 12/7/2021
Issuing Office
Current Status
CofO Issued on 11/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/10/2021 APPLICANT
Assigned to Plan Check Engineer 9/14/2021 LUKE GONZALES
Corrections Issued 9/14/2021 LUKE GONZALES
Applicant returned to address corrections 11/18/2021 LUKE GONZALES
Building Plans Picked Up 11/23/2021 APPLICANT
Issued 12/7/2021 APPLICANT
CofO in Progress 10/13/2023 MICHAEL LEWIS
CofO Issued 11/7/2023 DEROLD HAUFF
Permit Finaled 11/7/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/19/2021 THOMAS LANG
Roof/Waste drainage to street Cleared 9/19/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 9/21/2021 THOMAS LANG
Sewer availability Cleared 9/27/2021 THOMAS LANG

Contact Information

Contractor Jerahian Araz; Lic. No.: 1045340-B 250 N COLLEGE PARK DR F36      UPLAND, CA 91786
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/12/2022 Partial Inspection LILIANA PORTILLO
PLUMBING-Rough 9/12/2022 Conditional Approval LILIANA PORTILLO
Footing/Foundation/Slab 10/6/2022 Corrections Issued LILIANA PORTILLO
Footing/Foundation/Slab 10/24/2022 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 11/23/2022 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 12/16/2022 Approved LILIANA PORTILLO
Deputy Wood Construction 12/20/2022 Approved LILIANA PORTILLO
ELECTRICAL-Rough 1/23/2023 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 1/23/2023 Approved LILIANA PORTILLO
HVAC-Rough 1/23/2023 Approved LILIANA PORTILLO
PLUMBING-Rough 1/23/2023 Corrections Issued LILIANA PORTILLO
ELECTRICAL-Rough 1/30/2023 Approved LILIANA PORTILLO
PLUMBING-Rough 1/30/2023 Approved LILIANA PORTILLO
Sewer 1/30/2023 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 2/1/2023 Approved LILIANA PORTILLO
Green Building Rough 2/1/2023 Approved LILIANA PORTILLO
Interior/Exterior Lathing 2/1/2023 Partial Approval LILIANA PORTILLO
Insulation 2/28/2023 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 2/28/2023 Partial Approval ALEJANDRO DE ARTOLA
Shower Pan 2/28/2023 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 3/3/2023 Approved ALIZAH MAYAGOITIA
Final 6/7/2023 Corrections Issued STUART CHAPMAN
Green Building Final 6/7/2023 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 6/7/2023 SGSOV Approved STUART CHAPMAN
Smoke Detectors 6/7/2023 Approved STUART CHAPMAN
Final 9/12/2023 Conditional Approval MICHAEL LEWIS
Final 10/2/2023 Corrections Issued MICHAEL LEWIS
Final 10/12/2023 OK to Issue CofO MICHAEL LEWIS