3309 S PURDUE AVE 90066
Certificate Information: 3309 S PURDUE AVE 90066
- Application / Permit
- 21014-10000-04557
- Plan Check / Job No.
- B21LA16775
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) ADDITION, (N) ATTACHED TRELLIS, AND INTERIOR REMODEL TO (E) SFD WITH ATTACHED GARAGE
- Permit Issued
- Issued on 11/22/2021
- Issuing Office
- Current Status
- CofO Issued on 7/26/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/9/2021 | RAMA DABADGE |
| Corrections Issued | 9/9/2021 | RAMA DABADGE |
| Applicant returned to address corrections | 11/9/2021 | FERNANDO FLORES |
| Plan Check Approved | 11/18/2021 | FERNANDO FLORES |
| Issued | 11/22/2021 | APPLICANT |
| Building Plans Picked Up | 11/23/2021 | APPLICANT |
| CofO in Progress | 7/21/2022 | STEPHANIE SWANSON |
| CofO in Progress | 7/21/2022 | STEPHANIE SWANSON |
| Permit Finaled | 7/26/2022 | KENNETH NAGLE |
| CofO Issued | 7/26/2022 | KENNETH NAGLE |
| Permit Finaled | 7/26/2022 | KENNETH NAGLE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/29/2021 | PATRICK MISCHLICH |
| Specific Plan | Cleared | 11/1/2021 | PETE EYRE |
| Eng Process Fee Ord 176,300 | Cleared | 11/17/2021 | DENNIS BRAGIN |
| Roof/Waste drainage to street | Cleared | 11/17/2021 | DENNIS BRAGIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Alson,, Ken; Lic. No.: C41697 | 9744 MAPLE ST 201 BELLFLOWER, CA 90706 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/6/2022 | Approved | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 1/6/2022 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2022 | Partial Approval | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 3/9/2022 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2022 | Partial Approval | EVAN COOPER |
| HVAC-Rough | 3/9/2022 | Approved | EVAN COOPER |
| PLUMBING-Rough | 3/9/2022 | Approved | EVAN COOPER |
| Green Building Rough | 3/17/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 3/17/2022 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 3/23/2022 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 3/23/2022 | Approved | JOHNNY MIRANDA |
| Insulation | 3/23/2022 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 3/29/2022 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 3/29/2022 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 7/7/2022 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 7/7/2022 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 7/7/2022 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 7/7/2022 | Approved | HERBERT GIRON |
| Special/Order Compliance | 7/7/2022 | Partial Inspection | CLAYTON GRAHAM |
| ELECTRICAL-Final | 7/11/2022 | Approved | STEPHANIE SWANSON |
| Final | 7/11/2022 | Corrections Issued | STEPHANIE SWANSON |
| Gas Test | 7/11/2022 | Approved | STEPHANIE SWANSON |
| HVAC-Final | 7/11/2022 | Approved | STEPHANIE SWANSON |
| PLUMBING-Final | 7/11/2022 | Approved | STEPHANIE SWANSON |
| Service/Power Release | 7/11/2022 | Approved | STEPHANIE SWANSON |
| Special/Order Compliance | 7/11/2022 | Partial Inspection | HERBERT GIRON |
| Final | 7/21/2022 | OK to Issue CofO | STEPHANIE SWANSON |