12330 W BRADDOCK DR 90230
Certificate Information: 12330 W BRADDOCK DR 90230
- Application / Permit
- 21014-10000-04504
- Plan Check / Job No.
- B21LA16633
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 538 SF 2ND FLOOR ACCESSORY DWELLING UNIT ON TOP OF (E) 2-CAR GARAGE 366 SF AND (N) 193 SF 1ST FLOOR STORAGE ADDITION. ADU PER LAMC 12.22 A.33 (C) & (D)
- Permit Issued
- Issued on 9/27/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2021 | CHUNG-WEN CHUANG |
| Corrections Issued | 10/27/2021 | CHUNG-WEN CHUANG |
| Quality Review Completed | 11/2/2021 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 11/8/2021 | APPLICANT |
| Applicant returned to address corrections | 12/17/2021 | CHUNG-WEN CHUANG |
| Applicant returned to address corrections | 4/11/2022 | CHUNG-WEN CHUANG |
| Applicant returned to address corrections | 4/18/2022 | CHUNG-WEN CHUANG |
| Plan Check Approved | 5/2/2022 | CHUNG-WEN CHUANG |
| Issued | 9/27/2022 | APPLICANT |
| CofO in Progress | 1/2/2024 | JESUS PINEDA |
| CofO in Progress | 1/2/2024 | JESUS PINEDA |
| Permit Finaled | 1/5/2024 | DANIEL ORRANTE |
| CofO Issued | 1/5/2024 | DANIEL ORRANTE |
| Permit Finaled | 1/5/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 1/26/2022 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 1/26/2022 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 2/10/2022 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 2/10/2022 | HISASHI KOBAYAKAWA |
| Specific Plan | Cleared | 3/22/2022 | EDUARDO HERMOSO |
Contact Information
| Contractor | Empire Builder; Lic. No.: 1022769-B | 310 N COFFMAN ST ANAHEIM, CA 92805 |
| Engineer | Le,, Thang Huu; Lic. No.: S4978 | 507 MAGELLAN RD ARCADIA, CA 91007 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/1/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 12/1/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Sewer | 12/1/2022 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 12/1/2022 | Partial Approval | JESUS RODRIGUEZ |
| Special/Order Compliance | 12/7/2022 | Partial Inspection | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 12/27/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 12/27/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Rough | 12/27/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Special/Order Compliance | 12/27/2022 | Partial Inspection | CLAYTON GRAHAM |
| Wood Frame | 12/27/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2023 | Approved | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 3/9/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 4/28/2023 | Corrections Issued | HERBERT GIRON |
| Interior/Exterior Lathing | 4/28/2023 | Partial Approval | HERBERT GIRON |
| PLUMBING-Rough | 4/28/2023 | Corrections Issued | HERBERT GIRON |
| BUILDING-Rough-Frame | 5/3/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 5/3/2023 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 5/3/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 5/3/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 5/3/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 5/3/2023 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 5/16/2023 | Approved | JESUS RODRIGUEZ |
| Insulation | 5/16/2023 | Approved | JESUS RODRIGUEZ |
| Final | 11/30/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Final | 11/30/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 11/30/2023 | SGSOV Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 11/30/2023 | Approved | JESUS RODRIGUEZ |
| Final | 12/29/2023 | OK to Issue CofO | JESUS PINEDA |
| Green Building Final | 12/29/2023 | Approved | JESUS PINEDA |
| Service/Power Release | 12/29/2023 | Approved | JESUS PINEDA |