207 1/2 N ARDEN BLVD 90004
Certificate Information: 207 1/2 N ARDEN BLVD 90004
- Application / Permit
- 21014-10000-04501
- Plan Check / Job No.
- B21LA16604
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE TO ADU WITH AN ADDITION PER DETACHED ADU ORDINANCE (1-STORY)
- Permit Issued
- Issued on 4/4/2022
- Issuing Office
- Current Status
- CofO Issued on 2/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/3/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/6/2021 | CARLOS MONTES |
| Corrections Issued | 9/7/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 12/13/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 12/23/2021 | CARLOS MONTES |
| Plan Check Approved | 4/3/2022 | CARLOS MONTES |
| Issued | 4/4/2022 | APPLICANT |
| CofO in Progress | 2/2/2024 | RICHARD DOCKUS |
| Permit Finaled | 2/22/2024 | DEROLD HAUFF |
| CofO Issued | 2/22/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/7/2021 | AMAAN MALIK |
| Roof/Waste drainage to street | Cleared | 12/7/2021 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 12/13/2021 | AMAAN MALIK |
| Sewer availability | Cleared | 12/13/2021 | AMAAN MALIK |
| CPC | Cleared | 3/29/2022 | LYDIA CHAPMAN |
| CPC | Cleared | 3/29/2022 | LYDIA CHAPMAN |
| CPC | Cleared | 3/29/2022 | LYDIA CHAPMAN |
| HPOZ | Cleared | 3/29/2022 | LYDIA CHAPMAN |
Contact Information
| Architect | Zubieta,, Carlos M; Lic. No.: C33074 | 1745 ABBOT KINNEY BLVD 2ND FLOOR VENICE, CA 90291 |
| Architect | Zubieta,, Carlos M; Lic. No.: NA33074 | , |
| Contractor | G H Builders Inc; Lic. No.: 870657-B | , |
| Engineer | Keshishian,, Anthony; Lic. No.: C89551 | 2654 RISA D GLENDALE, CA 91208 |
| Engineer | Keshishian,, Anthony; Lic. No.: NA89551 | , |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Rough | 5/11/2022 | Approved | ARTHUR SARGSYAN |
| METHANE-Subgrade | 5/11/2022 | Approved | ARTHUR SARGSYAN |
| Underground Mechanical | 5/11/2022 | Approved | ARTHUR SARGSYAN |
| Deputy Methane Barrier | 5/16/2022 | Conditional Approval | ADAM ESCOTO |
| Deputy Methane Barrier | 5/18/2022 | Conditional Approval | FREDDIE RIVERA |
| Excavation/Setback/Form/Re-Bar | 5/20/2022 | Corrections Issued | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 6/1/2022 | Not Ready for Inspection | ADAM ESCOTO |
| Excavation/Setback/Form/Re-Bar | 6/6/2022 | Approved | ADAM ESCOTO |
| ELECTRICAL-Rough | 7/22/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 7/22/2022 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 7/26/2022 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 7/26/2022 | Approved | STUART CHAPMAN |
| Green Building Rough | 7/26/2022 | Not Ready for Inspection | STUART CHAPMAN |
| HVAC-Rough | 7/26/2022 | Approved | STUART CHAPMAN |
| Smoke Detectors | 7/26/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Insulation | 8/19/2022 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Rough | 9/1/2022 | Corrections Issued | JEFFREY MEAD |
| Insulation | 9/1/2022 | Approved | JEFFREY MEAD |
| Drywall Nailing | 9/8/2022 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 9/8/2022 | Partial Inspection | JOSEPH MCGARRY |
| Shower Pan | 9/8/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| Shower Pan | 9/12/2022 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 9/15/2022 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 9/19/2023 | Approved | RICHARD DOCKUS |
| Final | 9/19/2023 | Corrections Issued | RICHARD DOCKUS |
| Footing/Foundation/Slab | 9/19/2023 | Approved | RICHARD DOCKUS |
| Green Building Final | 9/19/2023 | Approved | RICHARD DOCKUS |
| Green Building Rough | 9/19/2023 | Approved | RICHARD DOCKUS |
| METHANE-Barrier | 9/19/2023 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 9/19/2023 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 9/19/2023 | Approved | RICHARD DOCKUS |
| Final | 11/13/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| Final | 11/27/2023 | Not Ready for Inspection | RICHARD DOCKUS |
| Final | 1/18/2024 | OK to Issue CofO | RICHARD DOCKUS |