940 S PATTON AVE 90731

Certificate Information: 940 S PATTON AVE 90731

Application / Permit
21014-10000-04496
Plan Check / Job No.
B21LA16549
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT ATTACHED GARAGE AND BREEZEWAY INTO A.D.U. PER STATE LAW.
Permit Issued
Issued on 5/30/2024
Issuing Office
San Pedro
Current Status
CofO Issued on 2/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/9/2021 APPLICANT
Assigned to Plan Check Engineer 9/10/2021 LAWRENCE QUIRANTE
Corrections Issued 9/13/2021 LAWRENCE QUIRANTE
Building Plans Picked Up 9/17/2021 APPLICANT
Plan Check Approved 7/28/2022 RAHEL BEYENE
Issued 5/30/2024 APPLICANT
CofO in Progress 2/26/2025 JOSEPH MCGARRY
Permit Finaled 2/26/2025 ANSON MAGLASANG
CofO Issued 2/26/2025 ANSON MAGLASANG
Permit Finaled 2/26/2025 ANSON MAGLASANG

Permit Application Clearance Information

Grading Pre-Inspection Cleared 11/1/2021 ALEXANDER HELFER
Address approval Cleared 4/12/2022 ERIK BEASLEY
Sewer availability Cleared 4/12/2022 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 4/14/2022 ERIK BEASLEY

Contact Information

Contractor Owner-Builder       ,
Engineer Hale,, Ronald Richard; Lic. No.: C17056 1869 PALACIOS DR      SAN PEDRO, CA 90732

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/5/2024 Approved BEN MOLSTAD
Pre-Inspection 9/5/2024 Approved BEN MOLSTAD
Underground Mechanical 9/5/2024 Approved BEN MOLSTAD
BUILDING-Rough-Frame 10/24/2024 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Rough 10/24/2024 Not Ready for Inspection JOSEPH MCGARRY
Green Building Rough 10/24/2024 Approved JOSEPH MCGARRY
PLUMBING-Rough 10/24/2024 Approved JOSEPH MCGARRY
Underground Mechanical 10/24/2024 Approved JOSEPH MCGARRY
ELECTRICAL-Rough 10/29/2024 Approved JOSEPH MCGARRY
HVAC-Rough 10/29/2024 Approved JOSEPH MCGARRY
Smoke Detectors 10/29/2024 Not Ready for Inspection JOSEPH MCGARRY
BUILDING-Rough-Frame 11/13/2024 Conditional Approval JOSEPH MCGARRY
Insulation 11/13/2024 Approved JOSEPH MCGARRY
Interior/Exterior Lathing 11/13/2024 Partial Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 12/11/2024 Approved JOSEPH MCGARRY
Drywall Nailing 12/11/2024 Approved JOSEPH MCGARRY
Green Building Rough 12/11/2024 Approved JOSEPH MCGARRY
Service/Power Release 12/11/2024 Approved JOSEPH MCGARRY
Final 2/21/2025 OK to Issue CofO JOSEPH MCGARRY
Footing/Foundation/Slab 2/21/2025 Approved JOSEPH MCGARRY
Green Building Final 2/21/2025 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 2/21/2025 SGSOV Not Required JOSEPH MCGARRY
Smoke Detectors 2/21/2025 Approved JOSEPH MCGARRY