4057 S BEETHOVEN ST 90066
Certificate Information: 4057 S BEETHOVEN ST 90066
- Application / Permit
- 21014-10000-04460
- Plan Check / Job No.
- B21LA16447
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan PROPOSED GROUND FLOOR AND SECOND FLOOR ADITION TO EXISTING DETACHED GARAGE TO CREATE AN ACCESSORY DWELLING UNIT WITH ROOF TOP DECK PER ORDINANCE.
- Permit Issued
- Issued on 9/23/2022
- Issuing Office
- Current Status
- CofO Issued on 11/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2021 | MICHAEL LOPEZ |
| Corrections Issued | 10/14/2021 | MICHAEL LOPEZ |
| Quality Review Completed | 10/18/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 10/29/2021 | CATHERINE CHEN |
| Applicant returned to address corrections | 11/11/2021 | TSE MING HUANG |
| Applicant returned to address corrections | 6/10/2022 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 8/24/2022 | MICHAEL LOPEZ |
| Plan Check Approved | 9/19/2022 | MICHAEL LOPEZ |
| Issued | 9/23/2022 | APPLICANT |
| CofO in Progress | 11/28/2023 | RICHARD STEINBACH |
| Permit Finaled | 11/29/2023 | DANIEL ORRANTE |
| CofO Issued | 11/29/2023 | DANIEL ORRANTE |
| Permit Finaled | 11/29/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 4/14/2022 | DINAH GARIN |
| Construction within easement | Cleared | 4/18/2022 | WALTER RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/18/2022 | DINAH GARIN |
| Sewer availability | Cleared | 4/18/2022 | DINAH GARIN |
| Specific Plan | Cleared | 5/12/2022 | PEDRO AYALA |
| Roof/Waste drainage to street | Cleared | 5/13/2022 | DINAH GARIN |
| Permit | Cleared | 8/16/2022 | DINAH GARIN |
| Trees in Parkway | Cleared | 8/30/2022 | ADALBERTO VERA |
Contact Information
| Architect | Mcnall,, Cameron C; Lic. No.: C24534 | 12034 NAVY STREET LOS ANGELES, CA 90066 |
| Contractor | Owner-Builder | , |
| Engineer | Baad,, Katherine Firestone; Lic. No.: C64669 | 5232 ZAKON RD TORRANCE, CA 90505 |
| Engineer | Farish,, William Crawford; Lic. No.: C30123 | 19432 CASTLEWOOD CR HUNTINGTON BEACH, CA 92648 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 1/20/2023 | Partial Approval | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 1/20/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 1/20/2023 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Rough | 1/20/2023 | Partial Approval | JESUS RODRIGUEZ |
| PLUMBING-Rough | 1/20/2023 | Partial Approval | JESUS RODRIGUEZ |
| Sewer | 1/20/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/29/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Deputy Wood Construction | 3/30/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/13/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 5/22/2023 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 5/22/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 5/22/2023 | Partial Approval | JESUS RODRIGUEZ |
| Sewer | 5/22/2023 | Conditional Approval | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 6/22/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 6/22/2023 | Approved | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 6/22/2023 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Green Building Rough | 6/22/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| HVAC-Rough | 6/22/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| PLUMBING-Rough | 6/22/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Pre-Inspection | 6/22/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Sewer | 6/22/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| HVAC-Rough | 7/3/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 7/3/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 7/3/2023 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Rough | 7/14/2023 | Approved | EVAN COOPER |
| Insulation | 7/14/2023 | Approved | EVAN COOPER |
| PLUMBING-Rough | 7/14/2023 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 7/27/2023 | Approved | BOBBY KEY |
| Drywall Nailing | 8/3/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 8/3/2023 | Approved | JESUS RODRIGUEZ |
| Special/Order Compliance | 8/3/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Verify Sprinkler Sign Off | 8/3/2023 | Approved | JESUS RODRIGUEZ |
| Pre-Inspection | 10/11/2023 | Partial Inspection | CLAYTON GRAHAM |
| ELECTRICAL-Final | 11/3/2023 | Not Ready for Inspection | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 11/9/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 11/9/2023 | Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 11/9/2023 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 11/22/2023 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 11/22/2023 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 11/22/2023 | Approved | JESUS RODRIGUEZ |
| Final | 11/22/2023 | Partial Approval | JESUS RODRIGUEZ |
| Green Building Final | 11/22/2023 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 11/22/2023 | Approved | JESUS RODRIGUEZ |
| Grounding or Bonding | 11/22/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 11/22/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 11/22/2023 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 11/22/2023 | SGSOV Approved | JESUS RODRIGUEZ |
| Service/Power Release | 11/22/2023 | Approved | JESUS RODRIGUEZ |