8606 W GUTHRIE AVE 90034

Certificate Information: 8606 W GUTHRIE AVE 90034

Application / Permit
21014-10000-04392
Plan Check / Job No.
B21LA16165
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New ground floor addition to the (E) detached garage and conversion of new addition into an ADU per ordinance 186,481.
Permit Issued
Issued on 11/24/2021
Issuing Office
Current Status
CofO Issued on 7/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/29/2021 APPLICANT
Assigned to Plan Check Engineer 8/31/2021 HELEN NGUYEN
Corrections Issued 8/31/2021 HELEN NGUYEN
Applicant returned to address corrections 11/1/2021 HELEN NGUYEN
Plan Check Approved 11/18/2021 HELEN NGUYEN
Issued 11/24/2021 APPLICANT
CofO in Progress 7/18/2022 EVAN COOPER
Permit Finaled 7/23/2022 DANIEL ORRANTE
CofO Issued 7/23/2022 DANIEL ORRANTE
Permit Finaled 7/23/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 9/10/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 9/16/2021 STEVE MELGAR
Sewer availability Cleared 9/16/2021 STEVE MELGAR
Roof/Waste drainage to street Cleared 11/9/2021 AMAAN MALIK

Contact Information

Contractor C-Unison Construction; Lic. No.: 651740-B 9734 LA TUNA CANYON RD      SUN VALLEY, CA 91352
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/22/2022 Approved EVAN COOPER
Pre-Inspection 3/22/2022 Approved EVAN COOPER
BUILDING-Rough-Frame 3/30/2022 Corrections Issued OGANES TARAKHCHYAN
BUILDING-Rough-Frame 4/4/2022 Partial Approval EVAN COOPER
Footing/Foundation/Slab 4/4/2022 Approved EVAN COOPER
PLUMBING-Rough 4/4/2022 Partial Approval EVAN COOPER
BUILDING-Rough-Frame 4/19/2022 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 4/19/2022 Partial Approval EVAN COOPER
Wood Frame 4/19/2022 Partial Approval EVAN COOPER
ELECTRICAL-Rough 4/22/2022 Approved EVAN COOPER
PLUMBING-Rough 4/22/2022 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 5/9/2022 Approved EVAN COOPER
Interior/Exterior Lathing 5/9/2022 Partial Approval EVAN COOPER
Rough-Elec/Plmb/HVAC 5/9/2022 Approved EVAN COOPER
Shower Pan 5/9/2022 Approved EVAN COOPER
Wood Frame 5/9/2022 Approved EVAN COOPER
Insulation 5/13/2022 Corrections Issued EVAN COOPER
Drywall Nailing 5/20/2022 Approved EVAN COOPER
Insulation 5/20/2022 Approved EVAN COOPER
BUILDING-Rough-Frame 6/30/2022 Approved EVAN COOPER
Final 6/30/2022 Corrections Issued EVAN COOPER
SGSOV-Seismic Gas S/O Valve 6/30/2022 SGSOV Not Ready EVAN COOPER
Smoke Detectors 6/30/2022 Not Ready for Inspection EVAN COOPER
Final 7/12/2022 Conditional Approval EVAN COOPER
SGSOV-Seismic Gas S/O Valve 7/12/2022 SGSOV Approved EVAN COOPER
Smoke Detectors 7/12/2022 Approved EVAN COOPER
ELECTRICAL-Final 7/15/2022 Approved EVAN COOPER
Final 7/15/2022 Conditional Approval EVAN COOPER
HVAC-Final 7/15/2022 Approved EVAN COOPER
PLUMBING-Final 7/15/2022 Approved EVAN COOPER