5222 N LIVE OAK VIEW AVE 90041

Certificate Information: 5222 N LIVE OAK VIEW AVE 90041

Application / Permit
21014-10000-04391
Plan Check / Job No.
B21LA16164
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED ADDITION TO SINGLE FAMILY DWELLING
Permit Issued
Issued on 6/28/2022
Issuing Office
Current Status
CofO Issued on 11/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/29/2021 APPLICANT
Assigned to Plan Check Engineer 9/1/2021 SINA KHOSRAVI
Corrections Issued 12/9/2021 SINA KHOSRAVI
Applicant returned to address corrections 12/29/2021 STANLEY RAAP
Applicant returned to address corrections 2/7/2022 RICARDO RAMIREZ
Building Plans Picked Up 4/14/2022 APPLICANT
Applicant returned to address corrections 6/6/2022 DANIEL SANJUAN
Plan Check Approved 6/21/2022 MINA HABILI
Issued 6/28/2022 APPLICANT
CofO in Progress 11/25/2025 RONNIE MEDINA
Permit Finaled 11/25/2025 DEROLD HAUFF
CofO Issued 11/25/2025 DEROLD HAUFF
Permit Finaled 11/25/2025 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 4/28/2022 KIRK LINKLATER
Eng Process Fee Ord 176,300 Cleared 5/16/2022 JEANETTE VONG
Low Impact Development Cleared 5/25/2022 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 5/26/2022 JEANETTE VONG
Sewer availability Cleared 6/6/2022 CINDY QI
GPI Written Notices Cleared 6/21/2022 SINA KHOSRAVI

Contact Information

Contractor Owner-Builder       ,
Engineer Gray,, Jason Michael; Lic. No.: S6466 4418 UNION ST      LA CANADA, CA 91011

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/21/2022 Conditional Approval CRAIG VAUGHAN
Footing/Foundation/Slab 10/20/2022 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 12/13/2022 Partial Approval CRAIG VAUGHAN
Green Building Rough 12/13/2022 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 12/13/2022 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 3/8/2023 Partial Approval CRAIG VAUGHAN
Green Building Rough 3/8/2023 Not Ready for Inspection CRAIG VAUGHAN
Deputy Drilled-In Anchors 3/15/2023 Conditional Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 4/10/2023 Partial Approval CRAIG VAUGHAN
Interior/Exterior Lathing 5/3/2023 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 7/17/2023 Corrections Issued CRAIG VAUGHAN
HVAC-Rough 7/17/2023 Approved CRAIG VAUGHAN
PLUMBING-Rough 7/17/2023 Corrections Issued CRAIG VAUGHAN
Rough-Elec/Plmb/HVAC 7/17/2023 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 7/24/2023 Approved CRAIG VAUGHAN
ELECTRICAL-Rough 7/24/2023 Approved CRAIG VAUGHAN
Green Building Rough 7/24/2023 Approved CRAIG VAUGHAN
PLUMBING-Rough 7/24/2023 Approved CRAIG VAUGHAN
Insulation 7/31/2023 Approved SCOTT FINNILA
Drywall Nailing 8/11/2023 Approved JOSH MEISTER
Interior/Exterior Lathing 10/26/2023 Approved JOSH MEISTER
Shower Pan 10/26/2023 Approved JOSH MEISTER
Final 5/20/2024 Corrections Issued CRAIG VAUGHAN
Green Building Final 5/20/2024 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 5/20/2024 SGSOV Not Ready CRAIG VAUGHAN
Smoke Detectors 5/20/2024 Approved CRAIG VAUGHAN
Final 11/24/2025 OK to Issue CofO RONNIE MEDINA
SGSOV-Seismic Gas S/O Valve 11/24/2025 SGSOV Approved RONNIE MEDINA