1430 S STEARNS DR 90035

Certificate Information: 1430 S STEARNS DR 90035

Application / Permit
21014-10000-04363
Plan Check / Job No.
B21LA16087
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PARTIAL INTERIOR REMODEL AND ADDITION TO CREATE NEW MASTER SUITE, OFFICE, AND DINING ROOM.
Permit Issued
Issued on 3/17/2022
Issuing Office
Current Status
CofO Issued on 8/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/26/2021 APPLICANT
Assigned to Plan Check Engineer 9/16/2021 VARAND SARKISIAN
Corrections Issued 9/20/2021 VARAND SARKISIAN
Quality Review Completed 9/22/2021 HANS SANTIAGO
Plan Check Approved 3/11/2022 VARAND SARKISIAN
Issued 3/17/2022 APPLICANT
Building Plans Picked Up 3/18/2022 APPLICANT
CofO in Progress 8/24/2023 JOSE AVILA
Permit Finaled 8/29/2023 DEROLD HAUFF
CofO Issued 8/29/2023 DEROLD HAUFF
Permit Finaled 8/29/2023 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 11/17/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 1/26/2022 CELINA MORENO
Hydrant and Access approval Cleared 2/16/2022 JOHN CONNEALLY
Low Impact Development Cleared 2/24/2022 TA ANH
Roof/Waste drainage to street Cleared 2/25/2022 TREVOR QUAN

Contact Information

Contractor Owner-Builder       ,
Engineer Messiha,, Hany Gamil; Lic. No.: C56766 19648 MULBERRY DR      WALNUT, CA 91789

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/3/2022 Conditional Approval JOSE AVILA
Footing/Foundation/Slab 5/4/2022 Corrections Issued STUART CHAPMAN
Deputy Reinf. Concrete 5/6/2022 Approved JOSE AVILA
BUILDING-Rough-Frame 5/23/2022 Partial Approval JOSE AVILA
Green Building Rough 5/23/2022 Not Ready for Inspection JOSE AVILA
METHANE-Rough 5/23/2022 Not Ready for Inspection JOSE AVILA
Underground Mechanical 5/23/2022 Approved JOSE AVILA
Wood Frame 5/27/2022 Partial Approval JOSE AVILA
Underground Mechanical 6/10/2022 Partial Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 6/15/2022 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 6/28/2022 Approved JOSE AVILA
ELECTRICAL-Rough 8/3/2022 Corrections Issued JOSE AVILA
HVAC-Rough 8/3/2022 Corrections Issued JOSE AVILA
PLUMBING-Rough 8/3/2022 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 8/9/2022 Approved JOSE AVILA
HVAC-Rough 8/9/2022 Approved JOSE AVILA
BUILDING-Rough-Frame 8/15/2022 Partial Approval JOSE AVILA
PLUMBING-Rough 8/15/2022 Approved JOSE AVILA
Deputy Wood Construction 8/16/2022 Conditional Approval JOSE AVILA
Insulation 8/23/2022 Approved JOSE AVILA
Interior/Exterior Lathing 8/23/2022 Approved JOSE AVILA
Shower Pan 8/23/2022 Approved JOSE AVILA
Drywall Nailing 8/31/2022 Partial Approval JOSE AVILA
Green Building Rough 8/31/2022 Approved JOSE AVILA
Interior/Exterior Lathing 8/31/2022 Approved JOSE AVILA
Structural Steel Frame 8/31/2022 Partial Inspection JOSE AVILA
BUILDING-Rough-Frame 12/29/2022 Approved JOSE AVILA
Footing/Foundation/Slab 12/29/2022 Approved JOSE AVILA
METHANE-Barrier 12/29/2022 Approved JOSE AVILA
METHANE-Final 12/29/2022 Approved JOSE AVILA
METHANE-Rough 12/29/2022 Approved JOSE AVILA
METHANE-Subgrade 12/29/2022 Approved JOSE AVILA
Drywall Nailing 1/10/2023 Approved JOSE AVILA
ELECTRICAL-Rough 1/10/2023 Corrections Issued JOSE AVILA
Green Building Final 1/10/2023 Corrections Issued JOSE AVILA
HVAC-Final 1/10/2023 Corrections Issued JOSE AVILA
PLUMBING-Final 1/10/2023 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 1/10/2023 SGSOV Approved JOSE AVILA
Smoke Detectors 1/10/2023 Corrections Issued JOSE AVILA
ELECTRICAL-Final 1/19/2023 Corrections Issued JOSE AVILA
Green Building Final 1/19/2023 Approved JOSE AVILA
Smoke Detectors 1/19/2023 Approved JOSE AVILA
Final 2/7/2023 Corrections Issued JOSE AVILA
Final 8/24/2023 OK to Issue CofO JOSE AVILA