1430 S STEARNS DR 90035
Certificate Information: 1430 S STEARNS DR 90035
- Application / Permit
- 21014-10000-04363
- Plan Check / Job No.
- B21LA16087
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PARTIAL INTERIOR REMODEL AND ADDITION TO CREATE NEW MASTER SUITE, OFFICE, AND DINING ROOM.
- Permit Issued
- Issued on 3/17/2022
- Issuing Office
- Current Status
- CofO Issued on 8/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/16/2021 | VARAND SARKISIAN |
| Corrections Issued | 9/20/2021 | VARAND SARKISIAN |
| Quality Review Completed | 9/22/2021 | HANS SANTIAGO |
| Plan Check Approved | 3/11/2022 | VARAND SARKISIAN |
| Issued | 3/17/2022 | APPLICANT |
| Building Plans Picked Up | 3/18/2022 | APPLICANT |
| CofO in Progress | 8/24/2023 | JOSE AVILA |
| Permit Finaled | 8/29/2023 | DEROLD HAUFF |
| CofO Issued | 8/29/2023 | DEROLD HAUFF |
| Permit Finaled | 8/29/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Sewer availability | Cleared | 11/17/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 1/26/2022 | CELINA MORENO |
| Hydrant and Access approval | Cleared | 2/16/2022 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 2/24/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 2/25/2022 | TREVOR QUAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Messiha,, Hany Gamil; Lic. No.: C56766 | 19648 MULBERRY DR WALNUT, CA 91789 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/3/2022 | Conditional Approval | JOSE AVILA |
| Footing/Foundation/Slab | 5/4/2022 | Corrections Issued | STUART CHAPMAN |
| Deputy Reinf. Concrete | 5/6/2022 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 5/23/2022 | Partial Approval | JOSE AVILA |
| Green Building Rough | 5/23/2022 | Not Ready for Inspection | JOSE AVILA |
| METHANE-Rough | 5/23/2022 | Not Ready for Inspection | JOSE AVILA |
| Underground Mechanical | 5/23/2022 | Approved | JOSE AVILA |
| Wood Frame | 5/27/2022 | Partial Approval | JOSE AVILA |
| Underground Mechanical | 6/10/2022 | Partial Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2022 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2022 | Approved | JOSE AVILA |
| ELECTRICAL-Rough | 8/3/2022 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 8/3/2022 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 8/3/2022 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 8/9/2022 | Approved | JOSE AVILA |
| HVAC-Rough | 8/9/2022 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 8/15/2022 | Partial Approval | JOSE AVILA |
| PLUMBING-Rough | 8/15/2022 | Approved | JOSE AVILA |
| Deputy Wood Construction | 8/16/2022 | Conditional Approval | JOSE AVILA |
| Insulation | 8/23/2022 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 8/23/2022 | Approved | JOSE AVILA |
| Shower Pan | 8/23/2022 | Approved | JOSE AVILA |
| Drywall Nailing | 8/31/2022 | Partial Approval | JOSE AVILA |
| Green Building Rough | 8/31/2022 | Approved | JOSE AVILA |
| Interior/Exterior Lathing | 8/31/2022 | Approved | JOSE AVILA |
| Structural Steel Frame | 8/31/2022 | Partial Inspection | JOSE AVILA |
| BUILDING-Rough-Frame | 12/29/2022 | Approved | JOSE AVILA |
| Footing/Foundation/Slab | 12/29/2022 | Approved | JOSE AVILA |
| METHANE-Barrier | 12/29/2022 | Approved | JOSE AVILA |
| METHANE-Final | 12/29/2022 | Approved | JOSE AVILA |
| METHANE-Rough | 12/29/2022 | Approved | JOSE AVILA |
| METHANE-Subgrade | 12/29/2022 | Approved | JOSE AVILA |
| Drywall Nailing | 1/10/2023 | Approved | JOSE AVILA |
| ELECTRICAL-Rough | 1/10/2023 | Corrections Issued | JOSE AVILA |
| Green Building Final | 1/10/2023 | Corrections Issued | JOSE AVILA |
| HVAC-Final | 1/10/2023 | Corrections Issued | JOSE AVILA |
| PLUMBING-Final | 1/10/2023 | Corrections Issued | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 1/10/2023 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 1/10/2023 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Final | 1/19/2023 | Corrections Issued | JOSE AVILA |
| Green Building Final | 1/19/2023 | Approved | JOSE AVILA |
| Smoke Detectors | 1/19/2023 | Approved | JOSE AVILA |
| Final | 2/7/2023 | Corrections Issued | JOSE AVILA |
| Final | 8/24/2023 | OK to Issue CofO | JOSE AVILA |