5861 W 1ST ST 90036
Certificate Information: 5861 W 1ST ST 90036
- Application / Permit
- 21014-10000-04361
- Plan Check / Job No.
- B21LA16080
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO DETACHED GARAGE AND CONVERT NEW ADU.
- Permit Issued
- Issued on 3/28/2022
- Issuing Office
- Current Status
- CofO Issued on 7/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2021 | JOE VO |
| Corrections Issued | 10/10/2021 | JOE VO |
| Quality Review Completed | 10/17/2021 | HERNAN ARREOLA |
| Plan Check Approved | 3/22/2022 | JOE VO |
| Issued | 3/28/2022 | APPLICANT |
| CofO in Progress | 7/7/2023 | LILIANA PORTILLO |
| CofO in Progress | 7/13/2023 | SCOTT FINNILA |
| Permit Finaled | 7/14/2023 | DEROLD HAUFF |
| CofO Issued | 7/14/2023 | DEROLD HAUFF |
| Permit Finaled | 7/14/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/25/2021 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 10/25/2021 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 11/2/2021 | STEVE MELGAR |
| Sewer availability | Cleared | 11/2/2021 | STEVE MELGAR |
| Construction near power lines | Cleared | 1/28/2022 | RIDWAN HARDY |
| Historic monument | Cleared | 2/2/2022 | MAX LODER |
| HPOZ | Cleared | 3/15/2022 | DANIEL MATA |
| ZI | Cleared | 3/15/2022 | DANIEL MATA |
Contact Information
| No Data Available. |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/29/2022 | Corrections Issued | JOSEPH MCGARRY |
| METHANE-Barrier | 6/29/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| METHANE-Subgrade | 6/29/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 6/29/2022 | Partial Inspection | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 8/1/2022 | Partial Inspection | JOSEPH MCGARRY |
| METHANE-Barrier | 8/1/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| METHANE-Subgrade | 8/1/2022 | Not Ready for Inspection | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 8/16/2022 | Partial Approval | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2022 | Approved | MICHAEL LEWIS |
| Green Building Rough | 8/16/2022 | Not Ready for Inspection | MICHAEL LEWIS |
| METHANE-Rough | 8/16/2022 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 8/22/2022 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 8/22/2022 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 8/22/2022 | Approved | MICHAEL LEWIS |
| Insulation | 8/24/2022 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 8/24/2022 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 8/29/2022 | Approved | MICHAEL LEWIS |
| Green Building Rough | 9/6/2022 | Approved | MICHAEL LEWIS |
| Interior/Exterior Lathing | 9/6/2022 | Approved | MICHAEL LEWIS |
| Shower Pan | 9/9/2022 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 10/25/2022 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Final | 10/25/2022 | Corrections Issued | MICHAEL LEWIS |
| Final | 10/25/2022 | Corrections Issued | MICHAEL LEWIS |
| Footing/Foundation/Slab | 10/25/2022 | Approved | MICHAEL LEWIS |
| Green Building Final | 10/25/2022 | Approved | MICHAEL LEWIS |
| HVAC-Final | 10/25/2022 | Corrections Issued | MICHAEL LEWIS |
| METHANE-Barrier | 10/25/2022 | Approved | MICHAEL LEWIS |
| METHANE-Subgrade | 10/25/2022 | Approved | MICHAEL LEWIS |
| PLUMBING-Final | 10/25/2022 | Corrections Issued | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 10/25/2022 | SGSOV Approved | MICHAEL LEWIS |
| Smoke Detectors | 10/25/2022 | Approved | MICHAEL LEWIS |
| Final | 3/31/2023 | Partial Inspection | MICHAEL LEWIS |
| Final | 5/3/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Final | 7/5/2023 | Approved | LILIANA PORTILLO |
| Final | 7/5/2023 | OK to Issue CofO | LILIANA PORTILLO |
| HVAC-Final | 7/5/2023 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 7/5/2023 | Approved | LILIANA PORTILLO |