2423 W RIDGEVIEW AVE 90041

Certificate Information: 2423 W RIDGEVIEW AVE 90041

Application / Permit
21014-10000-04343
Plan Check / Job No.
B21LA16034
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED REAR ADDITION TO EXISTING SFD FOR NEW DEN, BATHROOMS, KITCHEN AND DINING ROOM "COMPLY WITH DEPARTMENT ORDER effective date 08/06/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 6/17/2022
Issuing Office
Metro
Current Status
CofO in Progress on 10/17/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 9/2/2021 APPLICANT
Assigned to Plan Check Engineer 9/3/2021 DANIEL SANJUAN
Corrections Issued 9/4/2021 DANIEL SANJUAN
Applicant returned to address corrections 10/14/2021 DANIEL SANJUAN
Applicant returned to address corrections 12/4/2021 DANIEL SANJUAN
Applicant returned to address corrections 12/6/2021 DANIEL SANJUAN
Applicant returned to address corrections 2/4/2022 GEORGE ALVAREZ
Applicant returned to address corrections 3/22/2022 AUNG SOE
Applicant returned to address corrections 4/21/2022 ADAM HEGAZI
Building Plans Picked Up 5/9/2022 APPLICANT
Plan Check Approved 6/15/2022 RAHEL BEYENE
Issued 6/17/2022 APPLICANT
CofO in Progress 10/17/2022 RAUL VASQUEZ

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/22/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 1/24/2022 JEANETTE VONG
Grading Pre-Inspection Cleared 6/9/2022 KIRK LINKLATER

Contact Information

Contractor Owner-Builder       ,
Engineer Evangelista,, Gil Viernes; Lic. No.: S2422 749 N FEATHERWOOD DR      DIAMOND BAR, CA 91765

Inspector Information

DANIEL DELACRUZ, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO SIERRA, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT MINASSIANS, (323) 526-9348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/22/2022 Approved RAUL VASQUEZ
PLUMBING-Rough 6/22/2022 Partial Approval RAUL VASQUEZ
PLUMBING-Rough 7/8/2022 Not Ready for Inspection RAUL VASQUEZ
PLUMBING-Rough 7/13/2022 Approved RAUL VASQUEZ
BUILDING-Rough-Frame 7/29/2022 Not Ready for Inspection RAUL VASQUEZ
ELECTRICAL-Rough 7/29/2022 Not Ready for Inspection RAUL VASQUEZ
Green Building Rough 7/29/2022 Not Ready for Inspection RAUL VASQUEZ
BUILDING-Rough-Frame 8/4/2022 Approved RAUL VASQUEZ
Green Building Rough 8/4/2022 Approved RAUL VASQUEZ
Rough-Elec/Plmb/HVAC 8/4/2022 Approved RAUL VASQUEZ
Drywall Nailing 8/8/2022 Approved RAUL VASQUEZ
Final 10/5/2022 Conditional Approval RAUL VASQUEZ
Green Building Final 10/5/2022 Approved RAUL VASQUEZ
SGSOV-Seismic Gas S/O Valve 10/5/2022 SGSOV Approved RAUL VASQUEZ
Smoke Detectors 10/5/2022 Approved RAUL VASQUEZ