1228 S CURSON AVE 90019
Certificate Information: 1228 S CURSON AVE 90019
- Application / Permit
- 21014-10000-04340
- Plan Check / Job No.
- B21LA16004
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePlan Check* convert existing detached garage to ADU add attached trellis
- Permit Issued
- Issued on 4/11/2022
- Issuing Office
- Current Status
- CofO Issued on 10/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/25/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/30/2021 | ARSALAN SHABESTARI |
| Corrections Issued | 10/6/2021 | ARSALAN SHABESTARI |
| Quality Review Completed | 10/8/2021 | MICHAEL PEREZ |
| Applicant returned to address corrections | 11/13/2021 | ARSALAN SHABESTARI |
| Plan Check Approved | 1/4/2022 | ARSALAN SHABESTARI |
| Issued | 4/11/2022 | APPLICANT |
| CofO in Progress | 10/6/2023 | JOSE AVILA |
| Permit Finaled | 10/9/2023 | DEROLD HAUFF |
| CofO Issued | 10/9/2023 | DEROLD HAUFF |
| Permit Finaled | 10/9/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 10/9/2021 | WALTER RAMIREZ |
| Construction within easement | Cleared | 10/9/2021 | WALTER RAMIREZ |
| CPC | Cleared | 10/12/2021 | KENTON TRINH |
| Address approval | Cleared | 10/16/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 10/16/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 10/18/2021 | RENZ SORIANO |
Contact Information
| Architect | Wacht,, Michael Adam; Lic. No.: NA33626 | , |
| Contractor | Alexander Building Co; Lic. No.: 980164-B | 1809 PARK DRIVE LOS ANGELES, CA 90026 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/20/2022 | Approved | JOSE AVILA |
| Deputy Drilled-In Anchors | 4/28/2022 | Conditional Approval | JOSE AVILA |
| Footing/Foundation/Slab | 5/4/2022 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 5/10/2022 | Approved | JOSE AVILA |
| Deputy Drilled-In Anchors | 5/12/2022 | Conditional Approval | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 5/17/2022 | Approved | JOSE AVILA |
| Sewer | 5/17/2022 | Partial Approval | JOSE AVILA |
| Footing/Foundation/Slab | 6/7/2022 | Partial Inspection | JOSE AVILA |
| Sewer | 6/7/2022 | Approved | JOSE AVILA |
| Underground Mechanical | 6/15/2022 | Approved | JOSE AVILA |
| Piling/Pier/Caisson | 6/28/2022 | Approved | JOSE AVILA |
| Footing/Foundation/Slab | 6/29/2022 | Partial Inspection | JOSE AVILA |
| ELECTRICAL-Rough | 7/28/2022 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Rough | 7/28/2022 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 9/21/2022 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2022 | Partial Approval | JOSE AVILA |
| BUILDING-Rough-Frame | 11/9/2022 | Partial Approval | JOSE AVILA |
| ELECTRICAL-Rough | 11/9/2022 | Partial Approval | JOSE AVILA |
| HVAC-Rough | 11/9/2022 | Approved | JOSE AVILA |
| Insulation | 11/16/2022 | Approved | JOSE AVILA |
| Drywall Nailing | 11/23/2022 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 1/17/2023 | Approved | MICHAEL LEWIS |
| Shower Pan | 1/17/2023 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 3/24/2023 | Approved | JOSE AVILA |
| Green Building Final | 3/24/2023 | Approved | JOSE AVILA |
| Green Building Rough | 3/24/2023 | Approved | JOSE AVILA |
| METHANE-Final | 3/24/2023 | Approved | JOSE AVILA |
| METHANE-Rough | 3/24/2023 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 3/24/2023 | SGSOV Approved | JOSE AVILA |
| Smoke Detectors | 3/24/2023 | Approved | JOSE AVILA |
| Final | 5/10/2023 | Corrections Issued | JOSE AVILA |
| Final | 6/7/2023 | Partial Approval | JOSE AVILA |
| Final | 10/5/2023 | OK to Issue CofO | JOSE AVILA |