15706 W LUDLOW ST 91344

Certificate Information: 15706 W LUDLOW ST 91344

Application / Permit
21014-10000-04285
Plan Check / Job No.
B21LA15821
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REAR ADDITION TO SFD
Permit Issued
Issued on 2/17/2022
Issuing Office
Current Status
CofO Issued on 7/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/26/2021 APPLICANT
Assigned to Plan Check Engineer 9/1/2021 FERNANDO FLORES
Corrections Issued 9/1/2021 FERNANDO FLORES
Applicant returned to address corrections 10/28/2021 RICARDO RAMIREZ
Applicant returned to address corrections 11/5/2021 RICARDO RAMIREZ
Plan Check Approved 1/27/2022 KHUONG TRUONG
Issued 2/17/2022 APPLICANT
Building Plans Picked Up 2/26/2022 APPLICANT
CofO in Progress 6/21/2023 JAVIER RAMOS JR
Permit Finaled 7/18/2023 MICHAEL SMITH
CofO Issued 7/18/2023 MICHAEL SMITH
Permit Finaled 7/18/2023 MICHAEL SMITH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/29/2021 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 11/1/2021 JOSE DUARTE-DIAZ
Construction near power lines Cleared 1/20/2022 RIDWAN HARDY

Contact Information

Contractor Funes Construction Inc; Lic. No.: 1028108-B 14154 ERWIN ST APT 6      VAN NUYS, CA 91401
Engineer Medina,, Armando; Lic. No.: C83911 121 N VAIL AVE      MONTEBELLO, CA 90640

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/11/2022 Corrections Issued JAVIER RAMOS JR
Deputy Drilled-In Anchors 4/12/2022 Conditional Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 6/2/2022 Partial Approval JAVIER RAMOS JR
ELECTRICAL-Rough 6/2/2022 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 6/2/2022 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 6/2/2022 Approved JAVIER RAMOS JR
Green Building Rough 6/2/2022 Not Ready for Inspection JAVIER RAMOS JR
MERV13>=Rough 6/2/2022 Not Ready for Inspection JAVIER RAMOS JR
Deputy Wood Construction 6/3/2022 Conditional Approval JAVIER RAMOS JR
BUILDING-Rough-Frame 8/1/2022 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 8/1/2022 Approved JAVIER RAMOS JR
Green Building Rough 8/1/2022 Approved JAVIER RAMOS JR
Insulation 8/1/2022 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 8/1/2022 Partial Approval JAVIER RAMOS JR
MERV13>=Rough 8/1/2022 Approved JAVIER RAMOS JR
Drywall Nailing 9/8/2022 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 10/19/2022 SGSOV Not Ready JAVIER RAMOS JR
Final 1/19/2023 Corrections Issued JAVIER RAMOS JR
Green Building Final 1/19/2023 Approved JAVIER RAMOS JR
MERV13>=Final 1/19/2023 Not Ready for Inspection JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 1/19/2023 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 1/19/2023 Not Ready for Inspection JAVIER RAMOS JR
Final 6/20/2023 OK to Issue CofO JAVIER RAMOS JR
MERV13>=Final 6/20/2023 Approved JAVIER RAMOS JR
Smoke Detectors 6/20/2023 Approved JAVIER RAMOS JR