11445 W SATICOY ST 91605
Certificate Information: 11445 W SATICOY ST 91605
- Application / Permit
- 21014-10000-04273
- Plan Check / Job No.
- B21LA15767
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 1-STORY ADDITION TO AN EXISTING 1-STORY RESIDENCE TO CONSIST OF NEW KITCHEN, BATHROOM, CLOSET, AND LAUNDRY CLOSET.
- Permit Issued
- Issued on 10/19/2021
- Issuing Office
- Current Status
- CofO Issued on 8/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/24/2021 | SAMUEL GONZALEZ |
| Corrections Issued | 8/24/2021 | SAMUEL GONZALEZ |
| Building Plans Picked Up | 8/26/2021 | APPLICANT |
| Plan Check Approved | 9/7/2021 | JOSEPH RAFOLS |
| Issued | 10/19/2021 | APPLICANT |
| CofO in Progress | 6/22/2022 | CHRISTOPHER DELLEFIELD |
| Permit Finaled | 8/19/2022 | DANIEL ORRANTE |
| CofO Issued | 8/19/2022 | DANIEL ORRANTE |
| Permit Finaled | 8/19/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/27/2021 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 8/27/2021 | DAGOVERTO GUERRERO |
| Clean Up Green Up | Cleared | 8/30/2021 | KENTON TRINH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mayorga,, Jose Aguinaldo; Lic. No.: C50322 | 20457 OREY PL WINNETKA, CA 91306 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/18/2022 | Approved | JENNIFER RABUCHIN |
| Sewer | 3/30/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Underground Mechanical | 3/30/2022 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 4/4/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 4/4/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Rough-Elec/Plmb/HVAC | 4/4/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Insulation | 4/8/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Shower Pan | 4/8/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 4/15/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 4/15/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 4/20/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 6/21/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 6/21/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Final | 6/21/2022 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 6/21/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 6/21/2022 | Approved | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 6/21/2022 | SGSOV Approved | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 6/21/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 6/22/2022 | OK to Issue CofO | CHRISTOPHER DELLEFIELD |