4359 S KENYON AVE 90066
Certificate Information: 4359 S KENYON AVE 90066
- Application / Permit
- 21014-10000-04256
- Plan Check / Job No.
- B21LA15704
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- GROUND FLOOR AND SECOND FLOOR ADDITION TO (E) 2-STORY SFD. INTERIOR AND EXTERIOR STRUCTURAL REMODEL TO THE SFD PER PLAN.
- Permit Issued
- Issued on 10/26/2021
- Issuing Office
- Current Status
- CofO Issued on 12/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/9/2021 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 9/17/2021 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 9/23/2021 | JASON HEALEY |
| Building Plans Picked Up | 9/28/2021 | APPLICANT |
| Plan Check Approved | 10/26/2021 | MAHNAZ NOURHASHEMI |
| Issued | 10/26/2021 | APPLICANT |
| CofO in Progress | 12/20/2022 | HERBERT GIRON |
| Permit Finaled | 12/22/2022 | DANIEL ORRANTE |
| CofO Issued | 12/22/2022 | DANIEL ORRANTE |
| Permit Finaled | 12/22/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Low Impact Development | Cleared | 10/6/2021 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 10/7/2021 | TRACY TATE |
| Eng Process Fee Ord 176,300 | Cleared | 10/14/2021 | TRACY TATE |
| Sewer availability | Cleared | 10/14/2021 | TRACY TATE |
Contact Information
| Architect | Hamilton,, John Patrick; Lic. No.: C28865 | 12240 VENICE BLVD SUITE 25 LOS ANGELES, CA 90066 |
| Contractor | Silva Design Construction Inc; Lic. No.: 956083-B | 1659 N LAKE AVE #6 PASADENA, CA 91104 |
| Engineer | Tuchscher,, James Todd; Lic. No.: C77649 | 5503 E 2ND ST LONG BEACH, CA 90803 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/1/2021 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 11/18/2021 | Partial Approval | DAVID FEILER |
| PLUMBING-Rough | 11/18/2021 | Partial Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2022 | Approved | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 3/8/2022 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Rough | 3/8/2022 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Rough | 3/8/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Wood Frame | 3/8/2022 | Conditional Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 3/10/2022 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 3/10/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Insulation | 3/10/2022 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 3/10/2022 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 3/10/2022 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 3/22/2022 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 3/22/2022 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 4/15/2022 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 6/10/2022 | Approved | PATRICK QUALEY |
| Final | 6/10/2022 | Corrections Issued | PATRICK QUALEY |
| Gas Test | 6/10/2022 | Approved | PATRICK QUALEY |
| Green Building Final | 6/10/2022 | Not Ready for Inspection | PATRICK QUALEY |
| SGSOV-Seismic Gas S/O Valve | 6/10/2022 | SGSOV Not Ready | PATRICK QUALEY |
| Smoke Detectors | 6/10/2022 | Not Ready for Inspection | PATRICK QUALEY |
| Service/Power Release | 6/23/2022 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Final | 6/28/2022 | Corrections Issued | STEPHANIE SWANSON |
| Service/Power Release | 6/28/2022 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 8/8/2022 | Corrections Issued | STEPHANIE SWANSON |
| Final | 8/8/2022 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Final | 8/8/2022 | Not Ready for Inspection | STEPHANIE SWANSON |
| HVAC-Final | 8/8/2022 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Final | 8/8/2022 | Corrections Issued | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 8/8/2022 | SGSOV Not Ready | STEPHANIE SWANSON |
| Smoke Detectors | 8/8/2022 | Corrections Issued | STEPHANIE SWANSON |
| Pre-Inspection | 8/9/2022 | Not Ready for Inspection | HERBERT GIRON |
| HVAC-Final | 10/18/2022 | Not Ready for Inspection | HERBERT GIRON |
| PLUMBING-Final | 10/18/2022 | Not Ready for Inspection | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 10/18/2022 | SGSOV Not Ready | HERBERT GIRON |
| ELECTRICAL-Final | 12/19/2022 | Approved | HERBERT GIRON |
| Final | 12/19/2022 | OK to Issue CofO | HERBERT GIRON |
| Green Building Final | 12/19/2022 | Approved | HERBERT GIRON |
| HVAC-Final | 12/19/2022 | Approved | HERBERT GIRON |
| PLUMBING-Final | 12/19/2022 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 12/19/2022 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 12/19/2022 | Approved | HERBERT GIRON |