4005 1/2 E SEQUOIA ST 90039

Certificate Information: 4005 1/2 E SEQUOIA ST 90039

Application / Permit
21014-10000-04195
Plan Check / Job No.
B21LA15434
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
2 STORY ADDITION TO EXISTING 1 STORY ADU PER 12.22 A33 C & D, (The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.)
Permit Issued
Issued on 5/3/2022
Issuing Office
Current Status
CofO Issued on 4/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/17/2021 APPLICANT
Assigned to Plan Check Engineer 9/9/2021 STARR CHEN
Corrections Issued 9/15/2021 STARR CHEN
Quality Review Completed 9/23/2021 JASON HEALEY
Applicant returned to address corrections 1/12/2022 STARR CHEN
Applicant returned to address corrections 2/7/2022 STARR CHEN
Plan Check Approved 3/11/2022 STARR CHEN
Issued 5/3/2022 APPLICANT
Building Plans Picked Up 5/10/2022 APPLICANT
CofO in Progress 4/20/2023 SCOTT FINNILA
Permit Finaled 4/23/2023 DEROLD HAUFF
CofO Issued 4/23/2023 DEROLD HAUFF
Permit Finaled 4/23/2023 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/14/2021 RENZ SORIANO
Supp. Use District POD/CDO/TDO Cleared 10/18/2021 LOUIS ORTEGA
Sewer availability Cleared 11/16/2021 PAMELA TENEZA
Roof/Waste drainage to street Cleared 2/11/2022 JEANETTE VONG

Contact Information

Contractor Umholtz J R Framing; Lic. No.: 722480-B 177 E 22ND STREET 9      COSTA MESA, CA 92627
Engineer Xia,, Ji; Lic. No.: C89014 420 S MADISON AVE   APT 301    PASADENA, CA 91101

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/16/2022 Approved HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 5/16/2022 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 5/16/2022 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 5/19/2022 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 5/23/2022 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Rough 5/23/2022 Not Ready for Inspection OSVALDO PARAMO
Footing/Foundation/Slab 5/27/2022 Approved CRAIG VAUGHAN
PLUMBING-Rough 5/27/2022 Partial Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 6/10/2022 Partial Approval HAMIK HARTOUNIAN
Green Building Rough 6/10/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 6/20/2022 Corrections Issued HAMIK HARTOUNIAN
Pre-Inspection 7/27/2022 Partial Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 8/4/2022 Partial Approval HAMIK HARTOUNIAN
PLUMBING-Rough 8/4/2022 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 8/9/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 8/9/2022 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 8/9/2022 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 8/19/2022 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 9/6/2022 Partial Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 9/8/2022 Corrections Issued HAMIK HARTOUNIAN
Green Building Rough 9/8/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Wood Frame 9/8/2022 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 9/13/2022 Corrections Issued JEFFREY MEAD
Green Building Rough 9/13/2022 Corrections Issued JEFFREY MEAD
Wood Frame 9/13/2022 Not Ready for Inspection JEFFREY MEAD
Green Building Rough 9/16/2022 Approved HAMIK HARTOUNIAN
HVAC-Rough 9/16/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Wood Frame 9/16/2022 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 9/20/2022 Approved HAMIK HARTOUNIAN
Shower Pan 9/20/2022 Conditional Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 9/26/2022 Corrections Issued HAMIK HARTOUNIAN
HVAC-Rough 9/26/2022 Partial Approval HAMIK HARTOUNIAN
HVAC-Rough 9/28/2022 Corrections Issued HAMIK HARTOUNIAN
Insulation 9/28/2022 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 10/3/2022 Approved HAMIK HARTOUNIAN
HVAC-Rough 10/3/2022 Approved HAMIK HARTOUNIAN
Insulation 10/3/2022 Approved HAMIK HARTOUNIAN
Drywall Nailing 10/6/2022 Approved CHARLES BOGHOSKHAN
Interior/Exterior Lathing 10/6/2022 Approved CHARLES BOGHOSKHAN
Final 2/23/2023 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 2/23/2023 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 2/23/2023 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 2/23/2023 Approved HAMIK HARTOUNIAN
ELECTRICAL-Final 4/17/2023 Approved SCOTT FINNILA
Final 4/17/2023 OK to Issue CofO SCOTT FINNILA
Green Building Final 4/17/2023 Approved SCOTT FINNILA
HVAC-Final 4/17/2023 Approved SCOTT FINNILA
PLUMBING-Final 4/17/2023 Approved SCOTT FINNILA
Service/Power Release 4/20/2023 Approved SCOTT FINNILA