6235 W 83RD PL 90045
Certificate Information: 6235 W 83RD PL 90045
- Application / Permit
- 21014-10000-04184
- Plan Check / Job No.
- B21LA15376
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO EXISTING 1 STORY GARAGE AND CONVERT INTO 2 STORY ADU PER 12.22 A33 C & D
- Permit Issued
- Issued on 3/10/2022
- Issuing Office
- Current Status
- CofO Issued on 7/17/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2021 | STARR CHEN |
| Corrections Issued | 9/2/2021 | STARR CHEN |
| Building Plans Picked Up | 9/8/2021 | APPLICANT |
| Quality Review Completed | 10/15/2021 | EUGENE BARBEAU |
| Applicant returned to address corrections | 11/4/2021 | STARR CHEN |
| Applicant returned to address corrections | 1/14/2022 | STARR CHEN |
| Plan Check Approved | 2/23/2022 | STARR CHEN |
| Issued | 3/10/2022 | APPLICANT |
| CofO in Progress | 7/13/2023 | HERBERT GIRON |
| Permit Finaled | 7/17/2023 | DANIEL ORRANTE |
| CofO Issued | 7/17/2023 | DANIEL ORRANTE |
| Permit Finaled | 7/17/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 9/9/2021 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 9/9/2021 | SAUL GARCIA |
| Sewer availability | Cleared | 9/9/2021 | SAUL GARCIA |
| Roof/Waste drainage to street | Cleared | 9/24/2021 | SAUL GARCIA |
| Specific Plan | Cleared | 10/6/2021 | PEDRO AYALA |
| Hydrant and Access approval | Cleared | 12/18/2021 | ROBERT DUFF |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/28/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 8/9/2022 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 8/9/2022 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 8/24/2022 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2022 | Partial Approval | BOBBY KEY |
| Wood Frame | 10/18/2022 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Rough | 1/5/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 1/5/2023 | Corrections Issued | HERBERT GIRON |
| Underground Mechanical | 1/5/2023 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 2/7/2023 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Rough | 2/7/2023 | Approved | BOBBY KEY |
| Green Building Rough | 2/7/2023 | Approved | BOBBY KEY |
| HVAC-Rough | 2/7/2023 | Approved | BOBBY KEY |
| Insulation | 2/7/2023 | Approved | BOBBY KEY |
| PLUMBING-Rough | 2/7/2023 | Approved | BOBBY KEY |
| Sewer | 2/7/2023 | Not Ready for Inspection | BOBBY KEY |
| BUILDING-Rough-Frame | 2/15/2023 | Approved | BOBBY KEY |
| Drywall Nailing | 3/1/2023 | Approved | JOHN KIDWELL |
| Shower Pan | 3/7/2023 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 3/28/2023 | Approved | HERBERT GIRON |
| HVAC-Final | 4/14/2023 | Partial Approval | BOBBY KEY |
| HVAC-Rough | 4/14/2023 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 6/16/2023 | Approved | BOBBY KEY |
| Final | 6/16/2023 | Corrections Issued | BOBBY KEY |
| Green Building Final | 6/16/2023 | Approved | BOBBY KEY |
| HVAC-Final | 6/16/2023 | Approved | BOBBY KEY |
| PLUMBING-Final | 6/16/2023 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 6/16/2023 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 6/16/2023 | Approved | BOBBY KEY |
| Special/Order Compliance | 6/28/2023 | Corrections Issued | BOBBY KEY |
| Final | 7/13/2023 | OK to Issue CofO | HERBERT GIRON |