3315 S CLUB DR 90064

Certificate Information: 3315 S CLUB DR 90064

Application / Permit
21014-10000-04171
Plan Check / Job No.
B21LA15340
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED ADDITION OF COVERED PATIO TO SINGLE FAMILY DWELLING
Permit Issued
Issued on 10/26/2021
Issuing Office
Current Status
CofO Issued on 6/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/19/2021 APPLICANT
Assigned to Plan Check Engineer 8/25/2021 SINA KHOSRAVI
Corrections Issued 8/31/2021 SINA KHOSRAVI
Plan Check Approved 9/22/2021 SHANGQIN XIE
Issued 10/26/2021 APPLICANT
Building Plans Picked Up 10/27/2021 APPLICANT
CofO in Progress 6/21/2022 KEVIN SARGSYAN
Permit Finaled 6/30/2022 DANIEL ORRANTE
Permit Finaled 6/30/2022 DANIEL ORRANTE
CofO Issued 6/30/2022 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/14/2021 JONATHAN HOM
Roof/Waste drainage to street Cleared 9/15/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 9/16/2021 DINAH GARIN

Contact Information

Contractor Valencia Construction Company; Lic. No.: 1015167-B 12069 SMALLWOOD AVE      DOWNEY, CA 90242
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/16/2021 Approved JOHNNY MIRANDA
Footing/Foundation/Slab 11/16/2021 Approved JOHNNY MIRANDA
Wood Frame 12/9/2021 Conditional Approval EVAN COOPER
ELECTRICAL-Rough 12/21/2021 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Rough 1/24/2022 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Rough 1/31/2022 Corrections Issued KEVIN SARGSYAN
Interior/Exterior Lathing 2/3/2022 Not Ready for Inspection EVAN COOPER
BUILDING-Rough-Frame 2/9/2022 Partial Approval KEVIN SARGSYAN
ELECTRICAL-Rough 2/9/2022 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 2/9/2022 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 2/23/2022 Not Ready for Inspection JOHNNY MIRANDA
ELECTRICAL-Rough 2/28/2022 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 4/6/2022 Approved KEVIN SARGSYAN
Drywall Nailing 4/6/2022 Approved KEVIN SARGSYAN
Final 4/6/2022 Corrections Issued KEVIN SARGSYAN
Green Building Final 4/6/2022 Approved KEVIN SARGSYAN
Green Building Rough 4/6/2022 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 4/6/2022 SGSOV Approved KEVIN SARGSYAN
Smoke Detectors 4/6/2022 Not Ready for Inspection KEVIN SARGSYAN
Final 4/22/2022 Not Ready for Inspection KEVIN SARGSYAN
Smoke Detectors 4/22/2022 Approved KEVIN SARGSYAN
Final 5/19/2022 Not Ready for Inspection KEVIN SARGSYAN
Final 6/17/2022 OK to Issue CofO KEVIN SARGSYAN