8084-8086 N CHERRYSTONE AVE 91402
Certificate Information: 8084-8086 N CHERRYSTONE AVE 91402
- Application / Permit
- 21014-10000-04160
- Plan Check / Job No.
- B21LA15290
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT 50 S.F. PORTION OF (E) REC ROOM TO (N) STORAGE. CONVERT 16 S.F. PORTION OF (E) REC ROOM, (N) BEDROOM AND (N) CLSET. DEMO 117 S.F. TOTAL. CONVERT PORTION OF (E) HOUSE, GARAGE, STORAGE, REC ROOM AND ADDITION TO (N) 1,000 S.F. ADU.
- Permit Issued
- Issued on 11/12/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/26/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/16/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/20/2021 | RACHEL BEYENE |
| Corrections Issued | 8/23/2021 | RACHEL BEYENE |
| Applicant returned to address corrections | 9/14/2021 | RACHEL BEYENE |
| Applicant returned to address corrections | 9/28/2021 | RACHEL BEYENE |
| Plan Check Approved | 10/5/2021 | RAHEL BEYENE |
| Building Plans Picked Up | 10/6/2021 | APPLICANT |
| Issued | 11/12/2021 | APPLICANT |
| CofO in Progress | 9/9/2022 | JOHN HAYES |
| No Progress | 4/7/2023 | ROBERT GOLD |
| CofO in Progress | 5/24/2023 | ROBERT GOLD |
| CofO Issued | 5/26/2023 | MICHAEL SMITH |
| Permit Finaled | 5/26/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 9/7/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 9/7/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 9/8/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 9/9/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Seven Seas Construction Services Inc; Lic. No.: 1065345-B | 16350 VENTURA BLVD STE D527 LOS ANGELES, CA 91436 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/19/2021 | Partial Approval | GREGG CUMMINGS |
| Footing/Foundation/Slab | 12/6/2021 | Corrections Issued | GREGG CUMMINGS |
| Wood Frame | 12/6/2021 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 12/7/2021 | Partial Approval | GREGG CUMMINGS |
| Sewer | 12/7/2021 | Partial Approval | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 12/9/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 12/9/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Wood Frame | 12/9/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 12/16/2021 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2021 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 12/16/2021 | Approved | GREGG CUMMINGS |
| Sewer | 12/16/2021 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 2/3/2022 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 2/3/2022 | Corrections Issued | GREGG CUMMINGS |
| Green Building Rough | 2/3/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 2/3/2022 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 2/3/2022 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 2/7/2022 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Rough | 2/7/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 2/7/2022 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 2/7/2022 | SGSOV Not Ready | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 2/9/2022 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 2/9/2022 | Corrections Issued | GREGG CUMMINGS |
| Green Building Rough | 2/9/2022 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 2/9/2022 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 2/17/2022 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 2/17/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Pre-Inspection | 2/17/2022 | Corrections Issued | JENNIFER RABUCHIN |
| Insulation | 2/18/2022 | Not Ready for Inspection | WILLIAM WREN |
| BUILDING-Rough-Frame | 2/23/2022 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 2/23/2022 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 2/23/2022 | Approved | GREGG CUMMINGS |
| Insulation | 2/23/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 2/23/2022 | Approved | GREGG CUMMINGS |
| Insulation | 2/25/2022 | Corrections Issued | GREGG CUMMINGS |
| Interior/Exterior Lathing | 2/25/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Shower Pan | 2/25/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Interior/Exterior Lathing | 3/2/2022 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Insulation | 3/4/2022 | Approved | GREGG CUMMINGS |
| Special/Order Compliance | 3/4/2022 | Corrections Issued | GREGG CUMMINGS |
| Drywall Nailing | 3/9/2022 | Approved | WILLIAM WREN |
| Shower Pan | 3/9/2022 | Not Ready for Inspection | WILLIAM WREN |
| Interior/Exterior Lathing | 3/16/2022 | Approved | GREGG CUMMINGS |
| Shower Pan | 3/16/2022 | Corrections Issued | GREGG CUMMINGS |
| Shower Pan | 3/22/2022 | Approved | WILLIAM WREN |
| ELECTRICAL-Final | 6/7/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Final | 7/14/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 7/14/2022 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 7/14/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Final | 7/14/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Final | 7/14/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 7/14/2022 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 7/14/2022 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 8/30/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Final | 8/30/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Final | 8/30/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Final | 8/30/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Final | 8/30/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 8/30/2022 | SGSOV Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 9/1/2022 | Partial Approval | JACK KARGODORIAN |
| HVAC-Final | 9/1/2022 | Approved | JACK KARGODORIAN |
| PLUMBING-Final | 9/1/2022 | Corrections Issued | JACK KARGODORIAN |
| Final | 9/8/2022 | OK to Issue CofO | JOHN HAYES |
| Green Building Final | 9/8/2022 | Approved | JOHN HAYES |
| Special/Order Compliance | 4/7/2023 | Corrections Issued | ROBERT GOLD |