2429 S CLOY AVE 90291
Certificate Information: 2429 S CLOY AVE 90291
- Application / Permit
- 21014-10000-04132
- Plan Check / Job No.
- B21LA15192
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- RENOVATION TO AN EXISTING S.F.D. WITH ATTACHED GARAGE. ENLARGE EXISTING GARAGE (34 SF) AND RENOVATE PORTION TO (N) BATHROOM AND LAUNDRY ROOM. "COMPLY WITH DEPARTMENT ORDER effective date 03/23/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 6/23/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/23/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/14/2021 | RICARDO RAMIREZ |
| Corrections Issued | 10/15/2021 | RICARDO RAMIREZ |
| Plan Check Approved | 3/11/2022 | ADAM HEGAZI |
| Building Plans Picked Up | 3/17/2022 | APPLICANT |
| Issued | 6/23/2022 | APPLICANT |
| CofO in Progress | 2/6/2023 | ANDREW BEELI |
| Permit Finaled | 3/23/2026 | CLAUDIO MORENO |
| CofO Issued | 3/23/2026 | CLAUDIO MORENO |
| Permit Finaled | 3/23/2026 | CLAUDIO MORENO |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/26/2021 | NIKTA MOUSAVI |
| Roof/Waste drainage to street | Cleared | 10/26/2021 | NIKTA MOUSAVI |
| Miscellaneous | Cleared | 1/12/2022 | RYAN LY |
| Miscellaneous | Cleared | 1/12/2022 | RYAN LY |
| Coastal Zone | Cleared | 1/13/2022 | RYAN LY |
| Specific Plan | Cleared | 1/19/2022 | IRA BROWN |
| ZI | Cleared | 1/19/2022 | IRA BROWN |
Contact Information
| Architect | Thibodeau,, Robert E; Lic. No.: C25585 | 812 LINCOLN BLVD VENICE, CA 90291 |
| Contractor | Termini Mark; Lic. No.: 779890-B | 22365 PRAIRE RD LAKE FOREST, CA 92630 |
Inspector Information
| ROBERT GARTH, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN MATTILLO, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO RIVERA, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| EUSEBIO GUZMAN, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL REECE, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDREW BEELI, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/29/2022 | Approved | MARIAN PODPORA |
| Deputy Drilled-In Anchors | 7/19/2022 | Approved | JOHN MATTILLO |
| Footing/Foundation/Slab | 7/19/2022 | Corrections Issued | JOHN MATTILLO |
| METHANE-Barrier | 7/19/2022 | Corrections Issued | JOHN MATTILLO |
| METHANE-Subgrade | 7/19/2022 | Corrections Issued | JOHN MATTILLO |
| Footing/Foundation/Slab | 8/4/2022 | Partial Approval | JOHN MATTILLO |
| METHANE-Barrier | 8/4/2022 | Approved | JOHN MATTILLO |
| METHANE-Subgrade | 8/4/2022 | Approved | JOHN MATTILLO |
| Deputy Drilled-In Anchors | 9/2/2022 | Conditional Approval | MARIAN PODPORA |
| BUILDING-Rough-Frame | 9/7/2022 | Not Ready for Inspection | MARIAN PODPORA |
| Footing/Foundation/Slab | 9/7/2022 | Partial Approval | MARIAN PODPORA |
| Green Building Rough | 9/7/2022 | Not Ready for Inspection | MARIAN PODPORA |
| METHANE-Rough | 9/7/2022 | Not Ready for Inspection | MARIAN PODPORA |
| ELECTRICAL-Rough | 9/23/2022 | Corrections Issued | MARIAN PODPORA |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2022 | Partial Approval | MARIAN PODPORA |
| Green Building Rough | 9/23/2022 | Not Ready for Inspection | MARIAN PODPORA |
| METHANE-Rough | 9/23/2022 | Not Ready for Inspection | MARIAN PODPORA |
| PLUMBING-Rough | 9/23/2022 | Corrections Issued | MARIAN PODPORA |
| BUILDING-Rough-Frame | 9/30/2022 | Corrections Issued | MARIAN PODPORA |
| ELECTRICAL-Rough | 9/30/2022 | Approved | MARIAN PODPORA |
| Green Building Rough | 9/30/2022 | Corrections Issued | MARIAN PODPORA |
| Insulation | 9/30/2022 | Approved | MARIAN PODPORA |
| Interior/Exterior Lathing | 9/30/2022 | Not Ready for Inspection | MARIAN PODPORA |
| METHANE-Rough | 9/30/2022 | Approved | MARIAN PODPORA |
| PLUMBING-Rough | 9/30/2022 | Approved | MARIAN PODPORA |
| Wood Frame | 9/30/2022 | Not Ready for Inspection | MARIAN PODPORA |
| Drywall Nailing | 10/18/2022 | Approved | MARIAN PODPORA |
| ELECTRICAL-Rough | 10/18/2022 | Approved | MARIAN PODPORA |
| HVAC-Rough | 10/18/2022 | Approved | MARIAN PODPORA |
| BUILDING-Rough-Frame | 1/25/2023 | Approved | MARIAN PODPORA |
| Final | 1/25/2023 | Corrections Issued | MARIAN PODPORA |
| Footing/Foundation/Slab | 1/25/2023 | Approved | MARIAN PODPORA |
| Green Building Final | 1/25/2023 | Approved | MARIAN PODPORA |
| Green Building Rough | 1/25/2023 | Approved | MARIAN PODPORA |
| SGSOV-Seismic Gas S/O Valve | 1/25/2023 | SGSOV Approved | MARIAN PODPORA |
| Smoke Detectors | 1/25/2023 | Corrections Issued | MARIAN PODPORA |
| Final | 2/2/2023 | Not Ready for Inspection | ANDREW BEELI |
| Smoke Detectors | 2/2/2023 | Not Ready for Inspection | ANDREW BEELI |
| Final | 2/6/2023 | OK to Issue CofO | ANDREW BEELI |
| Smoke Detectors | 2/6/2023 | Approved | ANDREW BEELI |