6111 W HARGIS ST 90034
Certificate Information: 6111 W HARGIS ST 90034
- Application / Permit
- 21014-10000-04131
- Plan Check / Job No.
- B21LA15190
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-CAR ATTACHED GARAGE, 1ST AND 2ND STORY ADDITION AND MAJOR REMODEL TO (E) 1-STORY SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 5/26/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/2/2021 | DANIEL YIP |
| Corrections Issued | 9/7/2021 | DANIEL YIP |
| Quality Review Completed | 9/10/2021 | JASON HEALEY |
| Building Plans Picked Up | 9/14/2021 | APPLICANT |
| Plan Check Approved | 4/26/2022 | DANIEL YIP |
| Issued | 5/26/2022 | APPLICANT |
| CofO in Progress | 12/12/2025 | EVAN COOPER |
| Permit Finaled | 12/23/2025 | RICHARD STEINBACH |
| CofO Issued | 12/23/2025 | RICHARD STEINBACH |
| Permit Finaled | 12/23/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Permit | Cleared | 10/8/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 10/14/2021 | WALLIE JONG |
| Sewer availability | Cleared | 10/14/2021 | WALLIE JONG |
| Frnt yard landscape/Water mgmt | Cleared | 11/22/2021 | MAXFIELD VERMY |
| Trees in Parkway | Cleared | 2/16/2022 | ADALBERTO VERA |
| Low Impact Development | Cleared | 2/18/2022 | KHAING AYE |
| Roof/Waste drainage to street | Cleared | 3/1/2022 | WALLIE JONG |
| Miscellaneous | Cleared | 4/19/2022 | ALBERT TAM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/22/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Deputy Drilled-In Anchors | 10/6/2022 | Conditional Approval | EVAN COOPER |
| Footing/Foundation/Slab | 10/11/2022 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 1/26/2023 | Conditional Approval | JEREMY TODD |
| BUILDING-Rough-Frame | 4/20/2023 | Partial Approval | JEREMY TODD |
| Footing/Foundation/Slab | 4/20/2023 | Corrections Issued | JEREMY TODD |
| PLUMBING-Rough | 4/20/2023 | Partial Approval | JEREMY TODD |
| Insulation | 5/2/2023 | Partial Approval | JEREMY TODD |
| BUILDING-Rough-Frame | 5/22/2023 | Not Ready for Inspection | JEREMY TODD |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2023 | Partial Approval | JEREMY TODD |
| Deputy Wood Construction | 6/13/2023 | Conditional Approval | JEREMY TODD |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2023 | Approved | JEREMY TODD |
| Interior/Exterior Lathing | 2/1/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 2/2/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Gas Test | 2/2/2024 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Rough | 2/2/2024 | Partial Approval | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 2/27/2024 | Approved | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 3/11/2024 | Corrections Issued | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 3/11/2024 | Approved | MEL KHACHATOURIAN |
| Green Building Rough | 3/11/2024 | Approved | MEL KHACHATOURIAN |
| HVAC-Rough | 3/11/2024 | Corrections Issued | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 3/11/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 3/11/2024 | Approved | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 4/8/2024 | Corrections Issued | MEL KHACHATOURIAN |
| HVAC-Rough | 4/8/2024 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 4/8/2024 | Partial Approval | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 4/15/2024 | Approved | MEL KHACHATOURIAN |
| Insulation | 4/25/2024 | Partial Approval | MEL KHACHATOURIAN |
| Drywall Nailing | 5/23/2024 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 7/23/2024 | Corrections Issued | KIRK SANDERS |
| Shower Pan | 7/23/2024 | Corrections Issued | KIRK SANDERS |
| Interior/Exterior Lathing | 7/29/2024 | Approved | MEL KHACHATOURIAN |
| Shower Pan | 7/29/2024 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Final | 9/30/2025 | Corrections Issued | EVAN COOPER |
| Final | 9/30/2025 | Not Ready for Inspection | EVAN COOPER |
| Footing/Foundation/Slab | 9/30/2025 | Approved | EVAN COOPER |
| Gas Test | 9/30/2025 | Approved | EVAN COOPER |
| Green Building Final | 9/30/2025 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Final | 9/30/2025 | Not Ready for Inspection | EVAN COOPER |
| PLUMBING-Final | 9/30/2025 | Corrections Issued | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 9/30/2025 | SGSOV Approved | EVAN COOPER |
| Service/Power Release | 9/30/2025 | Not Ready for Inspection | EVAN COOPER |
| Smoke Detectors | 9/30/2025 | Not Ready for Inspection | EVAN COOPER |
| ELECTRICAL-Final | 12/8/2025 | Approved | EVAN COOPER |
| Final | 12/8/2025 | Corrections Issued | EVAN COOPER |
| Green Building Final | 12/8/2025 | Approved | EVAN COOPER |
| HVAC-Final | 12/8/2025 | Approved | EVAN COOPER |
| PLUMBING-Final | 12/8/2025 | Approved | EVAN COOPER |
| Service/Power Release | 12/8/2025 | Approved | EVAN COOPER |
| Smoke Detectors | 12/8/2025 | Approved | EVAN COOPER |
| Final | 12/12/2025 | OK to Issue CofO | EVAN COOPER |