12036 W ALLIN ST 90230

Certificate Information: 12036 W ALLIN ST 90230

Application / Permit
21014-10000-04118
Plan Check / Job No.
B21LA15159
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO GARAGE AND CONVERSION INTO A.D.U.
Permit Issued
Issued on 11/18/2021
Issuing Office
Current Status
CofO Issued on 9/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/13/2021 APPLICANT
Assigned to Plan Check Engineer 9/16/2021 JOE VO
Corrections Issued 9/18/2021 JOE VO
Quality Review Completed 10/6/2021 MICHAEL PEREZ
Plan Check Approved 11/15/2021 JOE VO
Issued 11/18/2021 APPLICANT
CofO in Progress 9/12/2022 JESUS RODRIGUEZ
Permit Finaled 9/22/2022 DANIEL ORRANTE
CofO Issued 9/22/2022 DANIEL ORRANTE
Permit Finaled 9/22/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 9/21/2021 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 9/23/2021 ANTHONY MAINEZ
Sewer availability Cleared 9/23/2021 ANTHONY MAINEZ
Roof/Waste drainage to street Cleared 10/29/2021 ANTHONY MAINEZ

Contact Information

Contractor My Home Builders Inc; Lic. No.: 1002927-B       ,
Engineer Dominguez,, Refugio; Lic. No.: NA50820       ,

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/2/2022 Approved ENRIQUE MIRELES
Sewer 3/2/2022 Partial Approval ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 3/15/2022 Corrections Issued JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 3/17/2022 Not Ready for Inspection PATRICK QUALEY
PLUMBING-Rough 3/17/2022 Corrections Issued PATRICK QUALEY
BUILDING-Rough-Frame 3/25/2022 Corrections Issued PATRICK QUALEY
Green Building Rough 3/25/2022 Approved PATRICK QUALEY
PLUMBING-Rough 3/25/2022 Corrections Issued PATRICK QUALEY
ELECTRICAL-Rough 3/31/2022 Partial Approval PATRICK QUALEY
Gas Test 3/31/2022 Corrections Issued PATRICK QUALEY
Special/Order Compliance 3/31/2022 Partial Inspection MICHAEL PELHAM
Sewer 4/18/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 4/28/2022 Corrections Issued JESUS RODRIGUEZ
Gas Test 4/28/2022 Not Ready for Inspection JESUS RODRIGUEZ
PLUMBING-Rough 4/28/2022 Not Ready for Inspection JESUS RODRIGUEZ
Pre-Inspection 5/3/2022 Partial Inspection PATRICK QUALEY
ELECTRICAL-Rough 5/9/2022 Approved PATRICK QUALEY
PLUMBING-Rough 5/9/2022 Approved PATRICK QUALEY
Underground Mechanical 5/9/2022 Partial Approval PATRICK QUALEY
Wood Frame 5/9/2022 Approved PATRICK QUALEY
Insulation 5/20/2022 Corrections Issued STEPHANIE SWANSON
Interior/Exterior Lathing 5/20/2022 Partial Approval STEPHANIE SWANSON
Insulation 5/25/2022 Conditional Approval CLAYTON GRAHAM
Drywall Nailing 6/2/2022 Partial Approval PATRICK QUALEY
Shower Pan 6/22/2022 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 6/29/2022 Not Ready for Inspection STEPHANIE SWANSON
Interior/Exterior Lathing 7/1/2022 Approved PATRICK QUALEY
ELECTRICAL-Final 7/27/2022 Corrections Issued HERBERT GIRON
BUILDING-Rough-Frame 9/1/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 9/1/2022 Corrections Issued JESUS RODRIGUEZ
Final 9/1/2022 Corrections Issued JESUS RODRIGUEZ
Green Building Final 9/1/2022 Approved JESUS RODRIGUEZ
HVAC-Final 9/1/2022 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Final 9/1/2022 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 9/1/2022 SGSOV Not Ready JESUS RODRIGUEZ
Smoke Detectors 9/1/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 9/7/2022 Corrections Issued HERBERT GIRON
Final 9/7/2022 Corrections Issued HERBERT GIRON
Gas Test 9/7/2022 Approved HERBERT GIRON
HVAC-Final 9/7/2022 Not Ready for Inspection HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 9/7/2022 SGSOV Approved HERBERT GIRON
ELECTRICAL-Final 9/9/2022 Approved JESUS RODRIGUEZ
Final 9/9/2022 Conditional Approval JESUS RODRIGUEZ
HVAC-Final 9/9/2022 Approved JESUS RODRIGUEZ
Service/Power Release 9/9/2022 Approved JESUS RODRIGUEZ