1503 N MCDONALD AVE 90744

Certificate Information: 1503 N MCDONALD AVE 90744

Application / Permit
21014-10000-04115
Plan Check / Job No.
B21LA15150
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(7) Garage - Private
Work Description
ADDITION (155 SF) TO (E) 1-CAR GARAGE (250 SF) AND ADDITION OF LAUNDRY AREA (38 SF). 1 OF 2
Permit Issued
Issued on 7/22/2022
Issuing Office
Metro
Current Status
CofO Issued on 5/9/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/24/2021 APPLICANT
Assigned to Plan Check Engineer 9/9/2021 VIVIAN LAO
Corrections Issued 9/16/2021 VIVIAN LAO
Quality Review Completed 10/5/2021 MICHAEL PEREZ
Building Plans Picked Up 11/18/2021 APPLICANT
Applicant returned to address corrections 4/15/2022 VIVIAN LAO
Applicant returned to address corrections 7/11/2022 VIVIAN LAO
Plan Check Approved 7/15/2022 VIVIAN LAO
Issued 7/22/2022 APPLICANT
CofO in Progress 4/28/2023 EUGENE CASSIDY
Permit Finaled 5/9/2023 DANIEL ORRANTE
CofO Issued 5/9/2023 DANIEL ORRANTE
Permit Finaled 5/9/2023 DANIEL ORRANTE

Permit Application Clearance Information

Sewer availability Cleared 5/18/2022 HUGO LOPEZ
Eng Process Fee Ord 176,300 Cleared 5/31/2022 HUGO LOPEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Cooke,, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/4/2022 Not Ready for Inspection EUGENE CASSIDY
Excavation/Setback/Form/Re-Bar 10/27/2022 Corrections Issued EUGENE CASSIDY
BUILDING-Rough-Frame 12/20/2022 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 12/20/2022 Approved EUGENE CASSIDY
Green Building Rough 12/20/2022 Not Ready for Inspection EUGENE CASSIDY
METHANE-Rough 12/20/2022 Approved EUGENE CASSIDY
PLUMBING-Rough 12/20/2022 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 4/27/2023 Approved EUGENE CASSIDY
Drywall Nailing 4/27/2023 Approved EUGENE CASSIDY
ELECTRICAL-Final 4/27/2023 Approved EUGENE CASSIDY
Final 4/27/2023 OK to Issue CofO EUGENE CASSIDY
Footing/Foundation/Slab 4/27/2023 Approved EUGENE CASSIDY
Green Building Final 4/27/2023 Approved EUGENE CASSIDY
Green Building Rough 4/27/2023 Approved EUGENE CASSIDY
HVAC-Final 4/27/2023 Approved EUGENE CASSIDY
METHANE-Barrier 4/27/2023 Approved EUGENE CASSIDY
METHANE-Subgrade 4/27/2023 Approved EUGENE CASSIDY
PLUMBING-Final 4/27/2023 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 4/27/2023 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 4/27/2023 Approved EUGENE CASSIDY