15437 S DENVER AVE 90248

Certificate Information: 15437 S DENVER AVE 90248

Application / Permit
21014-10000-04093
Plan Check / Job No.
B21LA15073
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1ST AND 2ND STORY ADDITION AND REMODEL TO (E) 1-STORY SINGLE FAMILY DWELLING.
Permit Issued
Issued on 12/8/2021
Issuing Office
Current Status
CofO Issued on 6/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/12/2021 APPLICANT
Assigned to Plan Check Engineer 9/16/2021 DANIEL YIP
Corrections Issued 9/22/2021 DANIEL YIP
Quality Review Completed 9/29/2021 ALLEN MANALANSAN
Applicant returned to address corrections 11/1/2021 DANIEL YIP
Plan Check Approved 11/15/2021 DANIEL YIP
Plan Check Approved 11/15/2021 YASHAR EMAMI
Issued 12/8/2021 APPLICANT
Building Plans Picked Up 12/10/2021 APPLICANT
CofO in Progress 6/9/2025 JOHN KLARIN
CofO Issued 6/9/2025 ANSON MAGLASANG
Permit Finaled 6/9/2025 ANSON MAGLASANG

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/25/2021 ERIK BEASLEY
Sewer availability Cleared 11/3/2021 ERIK BEASLEY
Roof/Waste drainage to street Cleared 11/5/2021 ERIK BEASLEY

Contact Information

Contractor Pacific Coast Builders; Lic. No.: 834794-B 9277OTTO ST      DOWNEY, CA 90240
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/12/2022 Conditional Approval ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 7/13/2022 Approved JOHN KLARIN
Footing/Foundation/Slab 7/13/2022 Approved JOHN KLARIN
METHANE-Barrier 7/13/2022 Approved JOHN KLARIN
METHANE-Subgrade 7/13/2022 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 7/27/2022 Partial Approval ANSON MAGLASANG
Deputy Wood Construction 8/18/2022 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 11/3/2022 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 11/21/2022 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 11/21/2022 Approved EUGENE CASSIDY
Green Building Rough 11/21/2022 Approved EUGENE CASSIDY
HVAC-Rough 11/21/2022 Partial Approval EUGENE CASSIDY
MERV13>=Rough 11/21/2022 Approved EUGENE CASSIDY
METHANE-Rough 11/21/2022 Approved EUGENE CASSIDY
PLUMBING-Rough 11/21/2022 Approved EUGENE CASSIDY
Insulation 12/27/2022 Approved JAMES CHAVEZ
Drywall Nailing 1/3/2023 Approved JAMES CHAVEZ
Interior/Exterior Lathing 1/3/2023 Approved JAMES CHAVEZ
Shower Pan 3/7/2023 Corrections Issued JAMES CHAVEZ
Shower Pan 3/20/2023 Approved JAMES CHAVEZ
Interior/Exterior Lathing 3/23/2023 Approved JAMES CHAVEZ
BUILDING-Rough-Frame 9/13/2023 Approved JOHN KLARIN
Final 9/13/2023 Corrections Issued JOHN KLARIN
Green Building Final 9/13/2023 Approved JOHN KLARIN
MERV13>=Final 9/13/2023 Approved JOHN KLARIN
SGSOV-Seismic Gas S/O Valve 9/13/2023 SGSOV Approved JOHN KLARIN
Smoke Detectors 9/13/2023 Approved JOHN KLARIN
BUILDING-Rough-Frame 2/10/2025 No Access for Inspection BEN MOLSTAD
Final 2/10/2025 No Access for Inspection BEN MOLSTAD
Verify Sprinkler Sign Off 2/10/2025 No Access for Inspection BEN MOLSTAD
BUILDING-Rough-Frame 2/14/2025 Not Ready for Inspection BEN MOLSTAD
Final 2/14/2025 Not Ready for Inspection BEN MOLSTAD
Verify Sprinkler Sign Off 2/14/2025 Not Ready for Inspection BEN MOLSTAD
BUILDING-Rough-Frame 6/3/2025 Not Ready for Inspection BEN MOLSTAD
Final 6/3/2025 Not Ready for Inspection BEN MOLSTAD
Verify Sprinkler Sign Off 6/3/2025 Not Ready for Inspection BEN MOLSTAD
BUILDING-Rough-Frame 6/6/2025 Approved JOHN KLARIN
ELECTRICAL-Final 6/6/2025 Approved JOHN KLARIN
Final 6/6/2025 OK to Issue CofO JOHN KLARIN
Green Building Final 6/6/2025 Approved JOHN KLARIN
HVAC-Final 6/6/2025 Approved JOHN KLARIN
PLUMBING-Final 6/6/2025 Approved JOHN KLARIN
Verify Sprinkler Sign Off 6/6/2025 Approved JOHN KLARIN