13003 W WELBY WAY 91606
Certificate Information: 13003 W WELBY WAY 91606
- Application / Permit
- 21014-10000-04084
- Plan Check / Job No.
- B21LA15037
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 1 STORY ADDITION AND INTERIOR REMODEL TO (E) SFD. REFRAME THE ROOF AT THE REAR OF BUILDING
- Permit Issued
- Issued on 11/8/2021
- Issuing Office
- Current Status
- CofO Issued on 10/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/16/2021 | FERNANDO FLORES |
| Corrections Issued | 8/17/2021 | FERNANDO FLORES |
| Applicant returned to address corrections | 8/25/2021 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 9/9/2021 | ADAM HEGAZI |
| Plan Check Approved | 11/3/2021 | SINA KHOSRAVI |
| Issued | 11/8/2021 | APPLICANT |
| Building Plans Picked Up | 11/10/2021 | APPLICANT |
| CofO in Progress | 10/4/2024 | OGANES TARAKHCHYAN |
| Permit Finaled | 10/7/2024 | DANIEL ORRANTE |
| CofO Issued | 10/7/2024 | DANIEL ORRANTE |
| Permit Finaled | 10/7/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/20/2021 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 10/25/2021 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 10/26/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Sarmiento Construction; Lic. No.: 819153-B | 13012 WELBY WAY NORTH HOLLYWOOD, CA 91606 |
| Engineer | Chan,, Albert F; Lic. No.: C61343 | 2261 PEPPERWOOD LN CORONA, CA 92882 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/2/2022 | Conditional Approval | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 5/4/2022 | Approved | CHRISTOPHE COCHRAN |
| Deputy Drilled-In Anchors | 6/7/2022 | Conditional Approval | CHRISTOPHE COCHRAN |
| Deputy Wood Construction | 6/9/2022 | Conditional Approval | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 6/10/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 6/15/2022 | Approved | ALAN MORELOS |
| Special/Order Compliance | 6/15/2022 | Corrections Issued | ALAN MORELOS |
| Pre-Inspection | 6/28/2022 | Corrections Issued | RAFAEL CORTES |
| Pre-Inspection | 7/5/2022 | Approved | RAFAEL CORTES |
| BUILDING-Rough-Frame | 7/18/2022 | Not Ready for Inspection | RAFAEL CORTES |
| ELECTRICAL-Rough | 7/18/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Green Building Rough | 7/18/2022 | Not Ready for Inspection | RAFAEL CORTES |
| PLUMBING-Rough | 7/18/2022 | Not Ready for Inspection | RAFAEL CORTES |
| ELECTRICAL-Rough | 7/22/2022 | Approved | RAFAEL CORTES |
| PLUMBING-Rough | 7/22/2022 | Approved | RAFAEL CORTES |
| BUILDING-Rough-Frame | 7/25/2022 | Approved | RAFAEL CORTES |
| Green Building Rough | 7/25/2022 | Approved | RAFAEL CORTES |
| HVAC-Rough | 7/25/2022 | Approved | RAFAEL CORTES |
| Insulation | 7/27/2022 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 7/27/2022 | Not Ready for Inspection | ASHLEY THOMPSON |
| Drywall Nailing | 8/1/2022 | Approved | RAFAEL CORTES |
| Interior/Exterior Lathing | 8/1/2022 | Approved | RAFAEL CORTES |
| ELECTRICAL-Final | 6/21/2023 | Corrections Issued | KIRK SANDERS |
| Final | 6/21/2023 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 6/21/2023 | Not Ready for Inspection | KIRK SANDERS |
| PLUMBING-Final | 6/21/2023 | Approved | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 6/21/2023 | SGSOV Approved | KIRK SANDERS |
| Smoke Detectors | 6/21/2023 | Corrections Issued | KIRK SANDERS |
| Final | 9/23/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Green Building Final | 9/23/2024 | Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 9/23/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 9/27/2024 | OK to Issue CofO | OGANES TARAKHCHYAN |