26017 S PRESIDENT AVE 90710

Certificate Information: 26017 S PRESIDENT AVE 90710

Application / Permit
21014-10000-04035
Plan Check / Job No.
B21LA14855
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION AT THE REAR OF THE EXISTING ONE STORY SFD.
Permit Issued
Issued on 1/7/2022
Issuing Office
Current Status
CofO Issued on 8/20/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/10/2021 APPLICANT
Assigned to Plan Check Engineer 8/13/2021 TSE MING HUANG
Corrections Issued 8/14/2021 TSE MING HUANG
Applicant returned to address corrections 11/3/2021 GEORGE ALVAREZ
Plan Check Approved 12/30/2021 TSE MING HUANG
Issued 1/7/2022 APPLICANT
Building Plans Picked Up 1/10/2022 APPLICANT
CofO in Progress 8/8/2022 EUGENE CASSIDY
Permit Finaled 8/20/2022 DEROLD HAUFF
CofO Issued 8/20/2022 DEROLD HAUFF
Permit Finaled 8/20/2022 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 9/3/2021 CHINH DINH
Sewer availability Cleared 9/3/2021 CHINH DINH
Eng Process Fee Ord 176,300 Cleared 9/7/2021 CHINH DINH
"Q" conditions Cleared 12/22/2021 MAYELA VILLA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/26/2022 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 3/14/2022 Partial Approval EUGENE CASSIDY
PLUMBING-Rough 3/14/2022 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 4/6/2022 Not Ready for Inspection EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 4/6/2022 Partial Approval EUGENE CASSIDY
BUILDING-Rough-Frame 4/11/2022 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 4/11/2022 Not Ready for Inspection EUGENE CASSIDY
Green Building Rough 4/11/2022 Approved EUGENE CASSIDY
PLUMBING-Rough 4/11/2022 Approved EUGENE CASSIDY
Drywall Nailing 4/14/2022 Approved EUGENE CASSIDY
ELECTRICAL-Rough 4/14/2022 Approved EUGENE CASSIDY
Insulation 4/14/2022 Approved EUGENE CASSIDY
Interior/Exterior Lathing 4/14/2022 Partial Approval EUGENE CASSIDY
Shower Pan 5/25/2022 Not Ready for Inspection EUGENE CASSIDY
Interior/Exterior Lathing 6/2/2022 Partial Approval EUGENE CASSIDY
Shower Pan 6/2/2022 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 6/23/2022 Approved EUGENE CASSIDY
Final 6/23/2022 Corrections Issued EUGENE CASSIDY
Green Building Final 6/23/2022 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 6/23/2022 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 6/23/2022 Approved EUGENE CASSIDY
ELECTRICAL-Final 8/4/2022 Approved EUGENE CASSIDY
Final 8/4/2022 OK to Issue CofO EUGENE CASSIDY
Green Building Final 8/4/2022 Approved EUGENE CASSIDY
HVAC-Final 8/4/2022 Approved EUGENE CASSIDY
PLUMBING-Final 8/4/2022 Approved EUGENE CASSIDY