3902 N PORTOLA AVE 90032

Certificate Information: 3902 N PORTOLA AVE 90032

Application / Permit
21014-10000-04029
Plan Check / Job No.
B21LA14831
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ONE STORY ADDITION TO REAR AND INTERIOR REMODEL TO (E) SFD DWELLING
Permit Issued
Issued on 10/20/2021
Issuing Office
Current Status
CofO Issued on 3/4/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/9/2021 APPLICANT
Assigned to Plan Check Engineer 8/13/2021 STANLEY RAAP
Corrections Issued 8/16/2021 STANLEY RAAP
Applicant returned to address corrections 9/8/2021 JESSE JIMENEZ
Applicant returned to address corrections 10/16/2021 FERNANDO FLORES
Plan Check Approved 10/20/2021 FERNANDO FLORES
Issued 10/20/2021 APPLICANT
Building Plans Picked Up 10/21/2021 APPLICANT
CofO in Progress 2/29/2024 LILIANA PORTILLO
Permit Finaled 3/4/2024 DEROLD HAUFF
Permit Finaled 3/4/2024 DEROLD HAUFF
CofO Issued 3/4/2024 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/21/2021 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 8/24/2021 THOMAS LANG
Grading Pre-Inspection Cleared 8/24/2021 PATRICK MISCHLICH

Contact Information

Contractor L A Green Designs; Lic. No.: 988980-B P O BOX 411603      LOS ANGELES, CA 90041
Engineer Esmaily-Radvar,, Shahrokh; Lic. No.: C66139 5 HODGENVILLE      IRVINE, CA 92620

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/8/2021 Approved JOSEPH MCGARRY
Footing/Foundation/Slab 11/8/2021 Approved JOSEPH MCGARRY
Underground Mechanical 11/30/2021 Partial Approval COREY HUPP
ELECTRICAL-Rough 1/28/2022 Approved OSVALDO PARAMO
HVAC-Rough 1/28/2022 Corrections Issued OSVALDO PARAMO
PLUMBING-Rough 1/28/2022 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 2/2/2022 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Rough 2/2/2022 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 2/7/2022 Approved COREY HUPP
Green Building Rough 2/7/2022 Approved COREY HUPP
Insulation 2/11/2022 Approved COREY HUPP
Drywall Nailing 2/16/2022 Approved COREY HUPP
Interior/Exterior Lathing 2/16/2022 Approved COREY HUPP
Final 3/21/2022 Corrections Issued AMY COLIN
Green Building Final 3/21/2022 Corrections Issued AMY COLIN
SGSOV-Seismic Gas S/O Valve 3/21/2022 SGSOV Not Ready AMY COLIN
Smoke Detectors 3/21/2022 Approved AMY COLIN
ELECTRICAL-Final 3/23/2022 Approved AMY COLIN
Final 3/23/2022 Corrections Issued AMY COLIN
Green Building Final 3/23/2022 Approved AMY COLIN
HVAC-Final 3/23/2022 Approved AMY COLIN
PLUMBING-Final 3/23/2022 Approved AMY COLIN
SGSOV-Seismic Gas S/O Valve 3/23/2022 SGSOV Approved AMY COLIN
Final 4/7/2022 Partial Approval AMY COLIN
Final 2/27/2024 OK to Issue CofO LILIANA PORTILLO