2024 S 10TH AVE 90018

Certificate Information: 2024 S 10TH AVE 90018

Application / Permit
21014-10000-04012
Plan Check / Job No.
B21LA14758
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADU addition to existing garage per CA Govt. Code 65852.2(e)(1)(B)
Permit Issued
Issued on 12/1/2021
Issuing Office
Current Status
CofO Issued on 7/27/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/9/2021 APPLICANT
Assigned to Plan Check Engineer 8/10/2021 SHANGQIN XIE
Corrections Issued 8/10/2021 SHANGQIN XIE
Applicant returned to address corrections 11/15/2021 TSE MING HUANG
Plan Check Approved 11/22/2021 TSE MING HUANG
Issued 12/1/2021 APPLICANT
Building Plans Picked Up 12/2/2021 APPLICANT
CofO in Progress 7/11/2022 WILLIAM MICHALAK
Permit Finaled 7/27/2022 BRUCE TODD
CofO Issued 7/27/2022 BRUCE TODD
Permit Finaled 7/27/2022 BRUCE TODD

Permit Application Clearance Information

Address approval Cleared 8/23/2021 RENZ SORIANO
Eng Process Fee Ord 176,300 Cleared 8/23/2021 RENZ SORIANO
Roof/Waste drainage to street Cleared 8/25/2021 RENZ SORIANO
Sewer availability Cleared 8/25/2021 RENZ SORIANO
Construction near power lines Cleared 10/14/2021 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

LUIS CORRAL, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
DONALD WONG, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
KIM DOEPPING, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM MICHALAK, (213) 252-3964 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/9/2021 Approved STUART CHAPMAN
PLUMBING-Rough 12/9/2021 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 1/24/2022 Corrections Issued WILLIAM MICHALAK
Green Building Rough 1/24/2022 Approved WILLIAM MICHALAK
Interior/Exterior Lathing 1/27/2022 Approved WILLIAM MICHALAK
Rough-Elec/Plmb/HVAC 2/8/2022 Corrections Issued WILLIAM MICHALAK
Gas Test 2/18/2022 Not Ready for Inspection WILLIAM MICHALAK
Insulation 2/18/2022 Approved WILLIAM MICHALAK
Drywall Nailing 3/1/2022 Approved WILLIAM MICHALAK
Shower Pan 3/9/2022 Approved WILLIAM MICHALAK
BUILDING-Rough-Frame 4/22/2022 Approved WILLIAM MICHALAK
ELECTRICAL-Final 4/22/2022 Not Ready for Inspection WILLIAM MICHALAK
Final 4/22/2022 Not Ready for Inspection WILLIAM MICHALAK
Gas Test 4/22/2022 Not Ready for Inspection WILLIAM MICHALAK
Green Building Final 4/22/2022 Approved WILLIAM MICHALAK
PLUMBING-Final 4/22/2022 Not Ready for Inspection WILLIAM MICHALAK
SGSOV-Seismic Gas S/O Valve 4/22/2022 SGSOV Approved WILLIAM MICHALAK
Service/Power Release 4/22/2022 Not Ready for Inspection WILLIAM MICHALAK
Smoke Detectors 4/22/2022 Approved WILLIAM MICHALAK
Final 5/6/2022 Partial Approval WILLIAM MICHALAK
Gas Test 5/6/2022 Approved WILLIAM MICHALAK
Final 5/13/2022 Conditional Approval WILLIAM MICHALAK