1434 W 184TH ST 90248

Certificate Information: 1434 W 184TH ST 90248

Application / Permit
21014-10000-03984
Plan Check / Job No.
B21LA14688
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED (E) GARAGE WITH ADDITION TO ADU PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 11/18/2022
Issuing Office
Metro
Current Status
CofO Issued on 11/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/5/2021 APPLICANT
Assigned to Plan Check Engineer 8/10/2021 RAHEL BEYENE
Corrections Issued 8/11/2021 RAHEL BEYENE
Applicant returned to address corrections 5/23/2022 LUKE GONZALES
Applicant returned to address corrections 6/3/2022 LUKE GONZALES
Plan Check Approved 6/24/2022 FERNANDO FLORES
Issued 11/18/2022 APPLICANT
CofO in Progress 11/15/2024 BEN MOLSTAD
CofO Issued 11/18/2024 ANSON MAGLASANG
Permit Finaled 11/18/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 10/4/2021 WALLIE JONG
Roof/Waste drainage to street Cleared 10/4/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 10/5/2021 WALLIE JONG
Construction near power lines Cleared 1/19/2022 RIDWAN HARDY
Hydrant and Access approval Cleared 2/19/2022 LAURINDA MEADE
Sewer availability Cleared 5/4/2022 ANA VILLA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 12/30/2022 Not Ready for Inspection JAMES CHAVEZ
Underground Mechanical 12/30/2022 Approved JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 4/4/2023 Partial Approval JAMES CHAVEZ
PLUMBING-Rough 4/4/2023 Not Ready for Inspection JAMES CHAVEZ
Underground Mechanical 4/4/2023 Approved JAMES CHAVEZ
Insulation 7/3/2023 Approved JAMES CHAVEZ
Drywall Nailing 8/4/2023 Approved JAMES CHAVEZ
Green Building Rough 8/4/2023 Approved JAMES CHAVEZ
Shower Pan 8/18/2023 Approved JAMES CHAVEZ
Underground Mechanical 8/18/2023 Partial Approval JAMES CHAVEZ
Underground Mechanical 9/29/2023 Partial Approval JAMES CHAVEZ
BUILDING-Rough-Frame 10/15/2024 Approved BEN MOLSTAD
Final 10/15/2024 Corrections Issued BEN MOLSTAD
Footing/Foundation/Slab 10/15/2024 Approved BEN MOLSTAD
Green Building Final 10/15/2024 Not Ready for Inspection BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 10/15/2024 SGSOV Not Ready BEN MOLSTAD
Smoke Detectors 10/15/2024 Not Ready for Inspection BEN MOLSTAD
Final 10/24/2024 Corrections Issued JOSEPH MCGARRY
Green Building Final 10/24/2024 Approved JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 10/24/2024 SGSOV Approved JOSEPH MCGARRY
Smoke Detectors 10/24/2024 Approved JOSEPH MCGARRY
Final 10/30/2024 Corrections Issued BEN MOLSTAD
Final 11/8/2024 Not Ready for Inspection BEN MOLSTAD
ELECTRICAL-Final 11/15/2024 Approved BEN MOLSTAD
Final 11/15/2024 OK to Issue CofO BEN MOLSTAD
HVAC-Final 11/15/2024 Approved BEN MOLSTAD
PLUMBING-Final 11/15/2024 Approved BEN MOLSTAD