3176 W PERLITA AVE 90039

Certificate Information: 3176 W PERLITA AVE 90039

Application / Permit
21014-10000-03970
Plan Check / Job No.
B21LA14660
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ONE STORY ADDITION TO REAR OF DWELLING TO ENLARGE BEDROOM AND CREATE ADDITIONAL BATHROOM AND STORAGE ROOM.
Permit Issued
Issued on 10/4/2021
Issuing Office
Current Status
CofO Issued on 8/20/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/5/2021 APPLICANT
Assigned to Plan Check Engineer 8/11/2021 RICARDO RAMIREZ
Corrections Issued 8/12/2021 RICARDO RAMIREZ
Plan Check Approved 9/23/2021 RICARDO RAMIREZ
Issued 10/4/2021 APPLICANT
Building Plans Picked Up 12/3/2021 APPLICANT
CofO in Progress 8/15/2022 HAMIK HARTOUNIAN
Permit Finaled 8/20/2022 DEROLD HAUFF
CofO Issued 8/20/2022 DEROLD HAUFF
Permit Finaled 8/20/2022 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/19/2021 CECILIO NAVARRO
Sewer availability Cleared 8/19/2021 CECILIO NAVARRO
Eng Process Fee Ord 176,300 Cleared 8/20/2021 CECILIO NAVARRO
"Q" conditions Cleared 9/1/2021 KENTON TRINH

Contact Information

Contractor Amce Design Build; Lic. No.: 919611-B 8301 E FLORENCE AVE SUITE 205      DOWNEY, CA 90240
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/8/2021 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 2/2/2022 No Access for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 2/15/2022 Corrections Issued HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 2/15/2022 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 2/15/2022 Approved HAMIK HARTOUNIAN
Wood Frame 2/15/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Interior/Exterior Lathing 2/18/2022 Corrections Issued JOSEPH MCGARRY
BUILDING-Rough-Frame 3/3/2022 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 3/3/2022 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 3/3/2022 Approved HAMIK HARTOUNIAN
Green Building Rough 3/3/2022 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 3/3/2022 Partial Approval HAMIK HARTOUNIAN
Insulation 3/8/2022 Approved HAMIK HARTOUNIAN
Drywall Nailing 4/4/2022 Approved HAMIK HARTOUNIAN
Gas Test 5/11/2022 Approved HAMIK HARTOUNIAN
Service/Power Release 7/1/2022 Not Ready for Inspection HAMIK HARTOUNIAN
Final 8/8/2022 Partial Inspection HAMIK HARTOUNIAN
Green Building Final 8/8/2022 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 8/8/2022 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 8/8/2022 Approved HAMIK HARTOUNIAN
Final 8/15/2022 OK to Issue CofO HAMIK HARTOUNIAN