12315 W PALMS BLVD 90066

Certificate Information: 12315 W PALMS BLVD 90066

Application / Permit
21014-10000-03967
Plan Check / Job No.
B21LA14654
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED ADDITIONS AT EASTERLY SIDE OF (E) SFD WITH ATTACHED GARAGE.
Permit Issued
Issued on 12/6/2021
Issuing Office
Current Status
CofO Issued on 8/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/5/2021 APPLICANT
Assigned to Plan Check Engineer 8/11/2021 LAWRENCE QUIRANTE
Corrections Issued 8/12/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 9/25/2021 AUNG SOE
Applicant returned to address corrections 10/16/2021 AUNG SOE
Plan Check Approved 10/18/2021 AUNG SOE
Building Plans Picked Up 10/19/2021 APPLICANT
Issued 12/6/2021 APPLICANT
CofO in Progress 8/26/2022 JOHNNY MIRANDA
Permit Finaled 8/30/2022 DANIEL ORRANTE
CofO Issued 8/30/2022 DANIEL ORRANTE
Permit Finaled 8/30/2022 DANIEL ORRANTE

Permit Application Clearance Information

Sewer availability Cleared 8/31/2021 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 9/1/2021 ANTHONY MAINEZ
Roof/Waste drainage to street Cleared 9/14/2021 ANTHONY MAINEZ
Grading Pre-Inspection Cleared 9/25/2021 LAWRENCE QUIRANTE

Contact Information

Architect Swift,, Nathan Andrew; Lic. No.: C28798 543 A S. RAYMOND AVE      PASADENA, CA 91105
Contractor Superior Home Builders Inc; Lic. No.: 875933-B 6569 CLEOMOORE AVE      WEST HILLS, CA 91307
Engineer Phillips,, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/17/2021 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 12/21/2021 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 1/13/2022 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 1/28/2022 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 1/28/2022 Partial Approval JUAN VALENZUELA
Green Building Rough 1/28/2022 Not Ready for Inspection JUAN VALENZUELA
PLUMBING-Rough 1/28/2022 Corrections Issued JUAN VALENZUELA
PLUMBING-Rough 2/7/2022 Approved JOHNNY MIRANDA
Wood Frame 2/14/2022 Approved OGANES TARAKHCHYAN
Insulation 2/17/2022 Approved JOHNNY MIRANDA
Drywall Nailing 3/1/2022 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 6/13/2022 Partial Approval KENNETH NAGLE
BUILDING-Rough-Frame 7/26/2022 Approved JOHNNY MIRANDA
Final 7/26/2022 Corrections Issued JOHNNY MIRANDA
Green Building Final 7/26/2022 Approved JOHNNY MIRANDA
Green Building Rough 7/26/2022 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 7/26/2022 SGSOV Approved JOHNNY MIRANDA
Smoke Detectors 7/26/2022 Approved JOHNNY MIRANDA
Final 8/22/2022 OK to Issue CofO JOHNNY MIRANDA
HVAC-Final 8/22/2022 Approved JOHNNY MIRANDA