2239 1/2 W BRIER AVE 90039

Certificate Information: 2239 1/2 W BRIER AVE 90039

Application / Permit
21014-10000-03960
Plan Check / Job No.
B21LA14622
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing detached garage to A.D.U. and 2nd story addition per LAMC 12.22.A.33(c) & (d). the LID clearance has been deferred. approval for LID requirement shall be obtained from LASAN prior to the issuance of certificate of occupancy
Permit Issued
Issued on 1/25/2022
Issuing Office
Current Status
CofO Issued on 3/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/9/2021 APPLICANT
Assigned to Plan Check Engineer 8/26/2021 ARSALAN SHABESTARI
Corrections Issued 8/28/2021 ARSALAN SHABESTARI
Quality Review Completed 9/11/2021 YOUNG KIM
Applicant returned to address corrections 1/4/2022 ARSALAN SHABESTARI
Plan Check Approved 1/17/2022 ARSALAN SHABESTARI
Issued 1/25/2022 APPLICANT
CofO in Progress 3/2/2023 THOMAS LOGRASSO
Permit Finaled 3/4/2023 DEROLD HAUFF
CofO Issued 3/4/2023 DEROLD HAUFF
Permit Finaled 3/4/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 9/10/2021 STEVE MELGAR
BHO/Hillside ordinance Cleared 9/10/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 9/13/2021 STEVE MELGAR
Sewer availability Cleared 9/16/2021 STEVE MELGAR
GPI Written Notices Cleared 10/4/2021 ALEXANDER HELFER
Roof/Waste drainage to street Cleared 12/22/2021 AMAAN MALIK
Grading Pre-Inspection Cleared 1/17/2022 ARSALAN SHABESTARI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/8/2022 Partial Inspection THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 2/28/2022 Not Ready for Inspection THOMAS LOGRASSO
Footing/Foundation/Slab 2/28/2022 Not Ready for Inspection THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 3/8/2022 Approved THOMAS LOGRASSO
Footing/Foundation/Slab 3/8/2022 Approved THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 3/15/2022 Conditional Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 3/17/2022 Partial Approval THOMAS LOGRASSO
PLUMBING-Rough 3/22/2022 Not Ready for Inspection THOMAS LOGRASSO
Insulation 3/25/2022 Partial Approval THOMAS LOGRASSO
PLUMBING-Rough 3/25/2022 Corrections Issued THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 3/29/2022 Partial Approval THOMAS LOGRASSO
PLUMBING-Rough 3/30/2022 Partial Inspection THOMAS LOGRASSO
Underground Mechanical 4/4/2022 Partial Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 4/8/2022 Corrections Issued THOMAS LOGRASSO
Sewer 4/11/2022 Partial Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 4/15/2022 Corrections Issued THOMAS LOGRASSO
Deputy Drilled-In Anchors 4/18/2022 Conditional Approval THOMAS LOGRASSO
ELECTRICAL-Rough 5/12/2022 Corrections Issued THOMAS LOGRASSO
HVAC-Rough 5/12/2022 Corrections Issued THOMAS LOGRASSO
PLUMBING-Rough 5/12/2022 Corrections Issued THOMAS LOGRASSO
BUILDING-Rough-Frame 5/19/2022 Corrections Issued THOMAS LOGRASSO
ELECTRICAL-Rough 5/19/2022 Approved THOMAS LOGRASSO
HVAC-Rough 5/19/2022 Approved THOMAS LOGRASSO
PLUMBING-Rough 5/19/2022 Partial Approval THOMAS LOGRASSO
Verify Sprinkler Sign Off 5/19/2022 Not Ready for Inspection THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 5/25/2022 Not Ready for Inspection THOMAS LOGRASSO
Special/Order Compliance 5/25/2022 Partial Inspection RYAN SALAZAR
BUILDING-Rough-Frame 6/3/2022 Not Ready for Inspection THOMAS LOGRASSO
Verify Sprinkler Sign Off 6/3/2022 Approved THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 6/6/2022 Not Ready for Inspection THOMAS LOGRASSO
Shower Pan 6/6/2022 Partial Approval THOMAS LOGRASSO
Underground Mechanical 6/6/2022 Not Ready for Inspection THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 6/8/2022 Partial Approval THOMAS LOGRASSO
Shower Pan 6/8/2022 Approved THOMAS LOGRASSO
Underground Mechanical 6/8/2022 Partial Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 6/9/2022 Not Ready for Inspection THOMAS LOGRASSO
Shower Pan 6/9/2022 Not Ready for Inspection THOMAS LOGRASSO
Underground Mechanical 6/9/2022 Not Ready for Inspection THOMAS LOGRASSO
Interior/Exterior Lathing 6/23/2022 Partial Approval HAMIK HARTOUNIAN
Drywall Nailing 6/27/2022 Not Ready for Inspection THOMAS LOGRASSO
Interior/Exterior Lathing 6/27/2022 Partial Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 8/30/2022 Approved THOMAS LOGRASSO
ELECTRICAL-Final 8/30/2022 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Final 8/30/2022 Not Ready for Inspection THOMAS LOGRASSO
ELECTRICAL-Final 9/7/2022 Not Ready for Inspection THOMAS LOGRASSO
HVAC-Final 9/7/2022 Not Ready for Inspection THOMAS LOGRASSO
ELECTRICAL-Final 9/19/2022 Not Ready for Inspection STUART CHAPMAN
Final 9/19/2022 Corrections Issued STUART CHAPMAN
HVAC-Final 9/19/2022 Not Ready for Inspection STUART CHAPMAN
ELECTRICAL-Final 9/28/2022 Not Ready for Inspection THOMAS LOGRASSO
Final 9/28/2022 Corrections Issued THOMAS LOGRASSO
HVAC-Final 9/28/2022 Not Ready for Inspection THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 9/28/2022 SGSOV Not Ready THOMAS LOGRASSO
Smoke Detectors 9/28/2022 Approved THOMAS LOGRASSO
Final 10/5/2022 Not Ready for Inspection THOMAS LOGRASSO
PLUMBING-Final 10/5/2022 Not Ready for Inspection THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 10/5/2022 SGSOV Not Ready THOMAS LOGRASSO
Final 10/31/2022 Not Ready for Inspection THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 10/31/2022 SGSOV Approved THOMAS LOGRASSO
Service/Power Release 10/31/2022 Not Ready for Inspection THOMAS LOGRASSO
Service/Power Release 2/23/2023 Approved DONALD CRICHLOW
Final 3/2/2023 OK to Issue CofO THOMAS LOGRASSO