1501 S CREST DR 90035
Certificate Information: 1501 S CREST DR 90035
- Application / Permit
- 21014-10000-03959
- Plan Check / Job No.
- B21LA14620
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 103 SF ADDITION - KITCHEN AND DINING TO BE ENLARGED AND REMODELED.
- Permit Issued
- Issued on 12/2/2021
- Issuing Office
- Current Status
- CofO Issued on 6/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/6/2021 | DANIEL SANJUAN |
| Corrections Issued | 8/6/2021 | DANIEL SANJUAN |
| Applicant returned to address corrections | 11/2/2021 | ZAW HAN |
| Plan Check Approved | 11/3/2021 | ZAW HAN |
| Building Plans Picked Up | 11/4/2021 | APPLICANT |
| Issued | 12/2/2021 | APPLICANT |
| CofO in Progress | 6/7/2025 | MICHAEL PELHAM |
| Permit Finaled | 6/7/2025 | RICHARD STEINBACH |
| CofO Issued | 6/7/2025 | RICHARD STEINBACH |
| Permit Finaled | 6/7/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/31/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 9/1/2021 | WALLIE JONG |
| Grading Pre-Inspection | Cleared | 11/2/2021 | ALEXANDER HELFER |
Contact Information
| Contractor | Southwest Construction And Home Improvement; Lic. No.: 831043-B | 2729 S ROBERTSON BLVD LOS ANGELES, CA 90034 |
| Engineer | Garcia,, Francisco Javier; Lic. No.: C76510 | 2705 S FREMONT AVE APT D ALHAMBRA, CA 91803 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/21/2021 | Corrections Issued | EVAN COOPER |
| BUILDING-Rough-Frame | 1/31/2022 | Not Ready for Inspection | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2022 | Not Ready for Inspection | EVAN COOPER |
| Green Building Rough | 1/31/2022 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Rough | 1/31/2022 | Not Ready for Inspection | EVAN COOPER |
| BUILDING-Rough-Frame | 2/3/2022 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2022 | Partial Approval | EVAN COOPER |
| Green Building Rough | 2/3/2022 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Rough | 2/3/2022 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 2/18/2022 | Partial Approval | DEANDRE HOFFMAN |
| PLUMBING-Rough | 2/18/2022 | Approved | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 2/23/2022 | Approved | EVAN COOPER |
| Drywall Nailing | 2/23/2022 | Approved | EVAN COOPER |
| Green Building Rough | 2/23/2022 | Approved | EVAN COOPER |
| Insulation | 2/23/2022 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 2/23/2022 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 6/6/2022 | SGSOV Not Ready | EVAN COOPER |
| Final | 6/9/2022 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 6/9/2022 | Approved | STEPHANIE SWANSON |
| Green Building Final | 6/9/2022 | Not Ready for Inspection | STEPHANIE SWANSON |
| METHANE-Barrier | 6/9/2022 | Approved | STEPHANIE SWANSON |
| METHANE-Subgrade | 6/9/2022 | Approved | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 6/9/2022 | SGSOV Approved | STEPHANIE SWANSON |
| Smoke Detectors | 6/9/2022 | Corrections Issued | STEPHANIE SWANSON |
| Final | 6/14/2022 | Corrections Issued | EVAN COOPER |
| Green Building Final | 6/14/2022 | Approved | EVAN COOPER |
| Smoke Detectors | 6/14/2022 | Approved | EVAN COOPER |
| Final | 6/7/2025 | OK to Issue CofO | MICHAEL PELHAM |