6245 N CARTWRIGHT AVE 91606
Certificate Information: 6245 N CARTWRIGHT AVE 91606
- Application / Permit
- 21014-10000-03907
- Plan Check / Job No.
- B21LA14461
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION AT REAR AND CONVERT DETACHED GARAGE TO ACCESSORY DWELLING UNIT AND UTILITY ROOM
- Permit Issued
- Issued on 2/17/2022
- Issuing Office
- Current Status
- CofO Issued on 12/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/1/2021 | JESSE JIMENEZ |
| Corrections Issued | 9/2/2021 | JESSE JIMENEZ |
| Applicant returned to address corrections | 11/3/2021 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 1/20/2022 | JOSEPH RAFOLS |
| Applicant returned to address corrections | 1/29/2022 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 2/3/2022 | APPLICANT |
| Plan Check Approved | 2/14/2022 | JAD BASMA |
| Issued | 2/17/2022 | APPLICANT |
| CofO in Progress | 8/8/2023 | JENNIFER RABUCHIN |
| No Progress | 9/19/2023 | ROBERT GOLD |
| CofO in Progress | 9/19/2023 | ROBERT GOLD |
| CofO in Progress | 12/8/2023 | JENNIFER RABUCHIN |
| CofO Issued | 12/19/2023 | RUBEN SALAS |
| Permit Finaled | 12/19/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 10/6/2021 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 12/10/2021 | CHRIS PARK |
| Construction within easement | Cleared | 12/11/2021 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 1/11/2022 | DAGOVERTO GUERRERO |
| Hydrant and Access approval | Cleared | 1/11/2022 | MATTHEW CRAIG |
| Sewer availability | Cleared | 1/11/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 1/13/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chan,, Terence Ka-Hing; Lic. No.: C48893 | 3579 E FOOTHILL BLVD #206 PASADENA, CA 91107 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/3/2022 | Partial Approval | CALEB MEISTER |
| Excavation/Setback/Form/Re-Bar | 5/10/2022 | Corrections Issued | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 5/25/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 6/1/2022 | Corrections Issued | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 6/15/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Excavation/Setback/Form/Re-Bar | 6/24/2022 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 6/24/2022 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 8/24/2022 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 8/24/2022 | Approved | JOHN HAYES |
| Green Building Rough | 8/24/2022 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 8/24/2022 | Approved | JOHN HAYES |
| PLUMBING-Rough | 8/24/2022 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 10/12/2022 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 10/12/2022 | Not Ready for Inspection | JOHN HAYES |
| Gas Test | 10/31/2022 | Approved | JOHN HAYES |
| Sewer | 10/31/2022 | Approved | JOHN HAYES |
| Underground Mechanical | 10/31/2022 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 11/7/2022 | Approved | JOHN HAYES |
| Green Building Rough | 11/7/2022 | Approved | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 11/7/2022 | Approved | JOHN HAYES |
| Insulation | 11/17/2022 | Not Ready for Inspection | JOHN HAYES |
| Interior/Exterior Lathing | 11/17/2022 | Partial Approval | JOHN HAYES |
| Shower Pan | 11/17/2022 | Approved | JOHN HAYES |
| Insulation | 11/30/2022 | Approved | JOHN HAYES |
| Drywall Nailing | 12/9/2022 | Approved | JORDAN KUTZLY |
| ELECTRICAL-Final | 7/10/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 7/10/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 7/10/2023 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 7/10/2023 | SGSOV Not Ready | JENNIFER RABUCHIN |
| Smoke Detectors | 7/10/2023 | Approved | JENNIFER RABUCHIN |
| Final | 7/27/2023 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 7/27/2023 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 7/27/2023 | SGSOV Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Final | 8/3/2023 | Approved | JENNIFER RABUCHIN |
| Final | 8/3/2023 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 8/3/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 8/3/2023 | Approved | JENNIFER RABUCHIN |
| Special/Order Compliance | 9/21/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 9/28/2023 | Corrections Issued | JENNIFER RABUCHIN |