1902 N HYPERION AVE 90027
Certificate Information: 1902 N HYPERION AVE 90027
- Application / Permit
- 21014-10000-03899
- Plan Check / Job No.
- B21LA14404
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (18) Private School
- Work Description
- CHANGE USE OF (E) SINGLE FAMILY DWELLING WITH BASEMENT TO A PRESCHOOL ( 2 TO 6 YEARS OLD) & INTERIOR & EXTERIOR T.I & ADDITION OF ATTACHED DECK TO REAR OF BUILDING .
- Permit Issued
- Issued on 5/16/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/26/2021 | GARO TELMI |
| Green Plans Picked Up | 8/31/2021 | APPLICANT |
| Corrections Issued | 9/1/2021 | GARO TELMI |
| Quality Review Completed | 9/2/2021 | KEN GILL |
| Building Plans Picked Up | 9/21/2021 | APPLICANT |
| Disabled Access Plans Picked Up | 9/21/2021 | APPLICANT |
| Applicant returned to address corrections | 10/7/2021 | GARO TELMI |
| Applicant returned to address corrections | 10/28/2021 | GARO TELMI |
| Applicant returned to address corrections | 11/16/2021 | GARO TELMI |
| Applicant returned to address corrections | 11/23/2021 | GARO TELMI |
| Applicant returned to address corrections | 12/8/2021 | GARO TELMI |
| Plan Check Approved | 5/13/2022 | GARO TELMI |
| Issued | 5/16/2022 | APPLICANT |
| CofO in Progress | 5/5/2023 | ERNESTO CORRAL |
| Permit Finaled | 5/5/2023 | ERNESTO CORRAL |
| CofO Issued | 5/5/2023 | ERNESTO CORRAL |
| Permit Finaled | 5/5/2023 | ERNESTO CORRAL |
Permit Application Clearance Information
| "Q" conditions | Cleared | 9/10/2021 | RUBEN VASQUEZ |
| Miscellaneous | Cleared | 9/10/2021 | RUBEN VASQUEZ |
| Green Code | Cleared | 9/16/2021 | AARON COSTA |
| Driveway location | Cleared | 9/21/2021 | TAIMOUR TANAVOLI |
| Eng Process Fee Ord 176,300 | Cleared | 10/15/2021 | NAZILA NOORIFAR |
| Sewer availability | Cleared | 10/15/2021 | NAZILA NOORIFAR |
| Grading Pre-Inspection | Cleared | 10/26/2021 | PATRICK MISCHLICH |
| DAS Clearance | Cleared | 4/28/2022 | GARO TELMI |
| Fire Marshal Fire Life Safety | Cleared | 5/12/2022 | MENOA AGHAJANI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Braud,, Dillon Clark; Lic. No.: C91374 | 5707 OAK GROVE AVE OAKLAND, CA 94618 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/19/2022 | Partial Approval | EDWIN GREGORYONA |
| Pre-Inspection | 5/23/2022 | No Access for Inspection | SORIN CIRSTOIU |
| Wood Frame | 5/27/2022 | Not Ready for Inspection | JONATHAN QUACH |
| Wood Frame | 7/26/2022 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 8/3/2022 | Partial Approval | JONATHAN QUACH |
| Insulation | 8/8/2022 | Approved | GREGORY POMISH |
| Drywall Nailing | 8/12/2022 | Approved | RUSSELL BONVOULOIR |
| Final | 3/21/2023 | Not Ready for Inspection | TIMOTHY POWELL |
| SGSOV-Seismic Gas S/O Valve | 3/21/2023 | SGSOV Approved | TIMOTHY POWELL |
| Smoke Detectors | 3/21/2023 | Approved | TIMOTHY POWELL |
| Wood Frame | 3/21/2023 | Approved | TIMOTHY POWELL |
| Special/Order Compliance | 3/28/2023 | Partial Inspection | TIMOTHY POWELL |
| Final | 5/4/2023 | OK to Issue CofO | TIMOTHY POWELL |