1428 S WARNER AVE 90024

Certificate Information: 1428 S WARNER AVE 90024

Application / Permit
21014-10000-03897
Plan Check / Job No.
B21LA14393
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ONE STORY ADDITION TO EXISTING ONE STORY HOUSE.
Permit Issued
Issued on 1/13/2022
Issuing Office
Valley
Current Status
CofO Issued on 1/20/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/3/2021 APPLICANT
Assigned to Plan Check Engineer 8/9/2021 TSE MING HUANG
Corrections Issued 8/9/2021 TSE MING HUANG
Applicant returned to address corrections 9/8/2021 FERNANDO FLORES
Applicant returned to address corrections 12/16/2021 TSE MING HUANG
Plan Check Approved 1/4/2022 JOSEPH RAFOLS
Building Plans Picked Up 1/6/2022 APPLICANT
Issued 1/13/2022 APPLICANT
CofO in Progress 1/10/2023 STEPHANIE SWANSON
Permit Finaled 1/20/2023 DANIEL ORRANTE
CofO Issued 1/20/2023 DANIEL ORRANTE
Permit Finaled 1/20/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/14/2021 RAYMOND MUGAMBWA
Metro Rail approval Cleared 9/16/2021 TSE MING HUANG
Sewer availability Cleared 10/15/2021 RAYMOND MUGAMBWA
Specific Plan Cleared 10/18/2021 FREDDY GARCIA
Low Impact Development Cleared 12/3/2021 JULIAN SUNG
Roof/Waste drainage to street Cleared 12/9/2021 RAYMOND MUGAMBWA
Grading Pre-Inspection Cleared 1/4/2022 TSE MING HUANG

Contact Information

Contractor A B C Advance Builder & Constructor Inc; Lic. No.: 989468-B 18017 CHATSWORTH STREET #140      GRANADA HILLS, CA 91344
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/25/2022 Approved BRENDAN LOONEY
METHANE-Barrier 1/25/2022 Approved BRENDAN LOONEY
METHANE-Subgrade 1/25/2022 Approved BRENDAN LOONEY
BUILDING-Rough-Frame 5/10/2022 Corrections Issued BRENDAN LOONEY
ELECTRICAL-Rough 5/10/2022 Approved BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 5/10/2022 Partial Approval BRENDAN LOONEY
Green Building Rough 5/10/2022 Not Ready for Inspection BRENDAN LOONEY
HVAC-Rough 5/10/2022 Corrections Issued BRENDAN LOONEY
METHANE-Rough 5/10/2022 Approved BRENDAN LOONEY
PLUMBING-Rough 5/10/2022 Approved BRENDAN LOONEY
Deputy Wood Construction 5/25/2022 Conditional Approval BRENDAN LOONEY
BUILDING-Rough-Frame 6/7/2022 Approved BRENDAN LOONEY
ELECTRICAL-Rough 6/7/2022 Approved BRENDAN LOONEY
HVAC-Rough 6/7/2022 Approved BRENDAN LOONEY
PLUMBING-Rough 6/7/2022 Approved BRENDAN LOONEY
Shower Pan 6/7/2022 Approved BRENDAN LOONEY
Insulation 6/15/2022 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 6/15/2022 Partial Approval CHRISTOPHER WILSON
Drywall Nailing 6/20/2022 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 6/20/2022 Approved CHRISTOPHER WILSON
BUILDING-Rough-Frame 12/29/2022 Approved ASHLEY THOMPSON
ELECTRICAL-Final 12/29/2022 Approved ASHLEY THOMPSON
Final 12/29/2022 Corrections Issued ASHLEY THOMPSON
Green Building Final 12/29/2022 Approved ASHLEY THOMPSON
Green Building Rough 12/29/2022 Approved ASHLEY THOMPSON
HVAC-Final 12/29/2022 Approved ASHLEY THOMPSON
PLUMBING-Final 12/29/2022 Approved ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 12/29/2022 SGSOV Approved ASHLEY THOMPSON
Smoke Detectors 12/29/2022 Corrections Issued ASHLEY THOMPSON
Final 1/10/2023 OK to Issue CofO STEPHANIE SWANSON
Smoke Detectors 1/10/2023 Approved STEPHANIE SWANSON