4954 N GLEN IRIS AVE 90041

Certificate Information: 4954 N GLEN IRIS AVE 90041

Application / Permit
21014-10000-03896
Plan Check / Job No.
B21LA14391
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
One-story Addition and Major Remodel to (E) one-story SFD. Building to be sprinklered w/ NFPA 13D. All work per engineered design.
Permit Issued
Issued on 12/9/2021
Issuing Office
Current Status
CofO Issued on 1/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/3/2021 APPLICANT
Assigned to Plan Check Engineer 8/9/2021 TSE MING HUANG
Corrections Issued 8/9/2021 TSE MING HUANG
Applicant returned to address corrections 12/7/2021 DANIEL ABRAMYAN
Issued 12/9/2021 APPLICANT
Building Plans Picked Up 12/13/2021 APPLICANT
CofO in Progress 1/11/2023 CRAIG VAUGHAN
Permit Finaled 1/18/2023 DEROLD HAUFF
CofO Issued 1/18/2023 DEROLD HAUFF
Permit Finaled 1/18/2023 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 8/25/2021 JEANIE LAM
Sewer availability Cleared 8/25/2021 JEANIE LAM
Construction near power lines Cleared 11/13/2021 RIDWAN HARDY
Low Impact Development Cleared 12/1/2021 TA ANH
Roof/Waste drainage to street Cleared 12/1/2021 CELINA MORENO
GPI Written Notices Cleared 12/7/2021 CHRISTOPHER KOMANCHECK
Grading Pre-Inspection Cleared 12/7/2021 TSE MING HUANG

Contact Information

Contractor Builder Point Construction; Lic. No.: 1059885-B 11445 PARAMOUNT BLVD SUITE H      DOWNEY, CA 90241
Engineer Madero,, Fidencio; Lic. No.: C81695 10002 PANGBORN AVE      DOWNEY, CA 90240

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/21/2022 Not Ready for Inspection CRAIG VAUGHAN
Excavation/Setback/Form/Re-Bar 1/27/2022 Approved CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 2/16/2022 Partial Approval COREY HUPP
PLUMBING-Rough 2/16/2022 Partial Approval COREY HUPP
Insulation 2/22/2022 No Access for Inspection CRAIG VAUGHAN
Insulation 2/23/2022 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 4/5/2022 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 4/5/2022 Approved CRAIG VAUGHAN
Green Building Rough 4/5/2022 Approved CRAIG VAUGHAN
HVAC-Rough 4/5/2022 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 4/5/2022 Not Ready for Inspection CRAIG VAUGHAN
BUILDING-Rough-Frame 4/7/2022 Partial Approval CRAIG VAUGHAN
HVAC-Rough 4/7/2022 Partial Approval CRAIG VAUGHAN
PLUMBING-Rough 4/7/2022 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 4/12/2022 Not Ready for Inspection CRAIG VAUGHAN
HVAC-Rough 4/12/2022 Approved CRAIG VAUGHAN
BUILDING-Rough-Frame 4/19/2022 Partial Approval CRAIG VAUGHAN
Interior/Exterior Lathing 4/19/2022 Partial Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 4/21/2022 Approved CRAIG VAUGHAN
Insulation 4/25/2022 Approved CHARLES BOGHOSKHAN
Drywall Nailing 5/2/2022 Approved CHARLES BOGHOSKHAN
Interior/Exterior Lathing 5/4/2022 Approved CHARLES BOGHOSKHAN
Interior/Exterior Lathing 5/25/2022 Approved CHARLES BOGHOSKHAN
Shower Pan 5/25/2022 Approved CHARLES BOGHOSKHAN
ELECTRICAL-Final 11/16/2022 Not Ready for Inspection CRAIG VAUGHAN
Gas Test 11/16/2022 Approved CRAIG VAUGHAN
HVAC-Final 11/16/2022 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Final 11/16/2022 Not Ready for Inspection CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 12/9/2022 SGSOV Not Ready BRIAN SULLIVAN
ELECTRICAL-Final 1/3/2023 No Access for Inspection CRAIG VAUGHAN
Final 1/3/2023 No Access for Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 1/3/2023 Approved CRAIG VAUGHAN
Green Building Final 1/3/2023 Approved CRAIG VAUGHAN
HVAC-Final 1/3/2023 No Access for Inspection CRAIG VAUGHAN
PLUMBING-Final 1/3/2023 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 1/3/2023 SGSOV Not Ready CRAIG VAUGHAN
Service/Power Release 1/3/2023 Not Ready for Inspection CRAIG VAUGHAN
Smoke Detectors 1/3/2023 Not Ready for Inspection CRAIG VAUGHAN
Final 1/6/2023 Corrections Issued CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 1/6/2023 SGSOV Approved CRAIG VAUGHAN
Service/Power Release 1/6/2023 Approved CRAIG VAUGHAN
Smoke Detectors 1/6/2023 Approved CRAIG VAUGHAN
Final 1/9/2023 Corrections Issued CRAIG VAUGHAN
Final 1/10/2023 OK to Issue CofO CRAIG VAUGHAN