2341 S CLOVERDALE AVE 90016

Certificate Information: 2341 S CLOVERDALE AVE 90016

Application / Permit
21014-10000-03887
Plan Check / Job No.
B21LA14361
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan. Ground floor addition to an (E) detached garage and conversion of entire building into a ADU per ordinance 186,481.
Permit Issued
Issued on 11/29/2022
Issuing Office
Current Status
CofO Issued on 8/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/2/2021 APPLICANT
Assigned to Plan Check Engineer 8/4/2021 HELEN NGUYEN
Corrections Issued 8/4/2021 HELEN NGUYEN
Plan Check Approved 3/20/2022 JOE VO
Issued 11/29/2022 APPLICANT
CofO in Progress 8/5/2025 ARTHUR NEGRETE
Permit Finaled 8/24/2025 DEROLD HAUFF
CofO Issued 8/24/2025 DEROLD HAUFF
Permit Finaled 8/24/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/21/2021 RENZ SORIANO
Construction near power lines Cleared 12/30/2021 WALTER RAMIREZ
Low Impact Development Cleared 1/21/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 2/7/2022 CINDY QI
Eng Process Fee Ord 176,300 Cleared 3/11/2022 PAMELA TENEZA
Sewer availability Cleared 3/11/2022 PAMELA TENEZA

Contact Information

Contractor Owner-Builder       ,
Engineer Carrillo,, Jesus Eduardo; Lic. No.: C77737 8207 BROOKGREEN RD      DOWNEY, CA 90240

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 12/10/2022 Approved MORRIS JACKSON
Excavation/Setback/Form/Re-Bar 12/16/2022 Approved JOSE AVILA
Footing/Foundation/Slab 12/16/2022 Approved JOSE AVILA
Special/Order Compliance 12/19/2022 Approved JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 1/9/2023 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 1/12/2023 Conditional Approval FREDDIE RIVERA
PLUMBING-Rough 1/19/2023 Approved JOSE AVILA
ELECTRICAL-Rough 1/25/2023 Corrections Issued JOSE AVILA
HVAC-Rough 1/25/2023 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 3/31/2023 Corrections Issued JOSE AVILA
HVAC-Rough 3/31/2023 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 4/17/2023 Partial Approval JOSE AVILA
ELECTRICAL-Rough 4/17/2023 Approved JOSE AVILA
Green Building Rough 4/17/2023 Approved JOSE AVILA
HVAC-Rough 4/17/2023 Partial Approval JOSE AVILA
BUILDING-Rough-Frame 4/18/2023 Partial Approval JOSE AVILA
ELECTRICAL-Rough 4/18/2023 Approved JOSE AVILA
MERV13>=Rough 4/18/2023 Approved JOSE AVILA
Insulation 4/27/2023 Approved JOSE AVILA
Drywall Nailing 5/2/2023 Approved JOSE AVILA
PLUMBING-Rough 3/28/2024 Not Ready for Inspection STUART CHAPMAN
PLUMBING-Rough 4/3/2024 Not Ready for Inspection RICHARD DOCKUS
BUILDING-Rough-Frame 6/11/2024 Approved ARTHUR NEGRETE
ELECTRICAL-Rough 6/11/2024 Approved ARTHUR NEGRETE
Final 6/11/2024 Corrections Issued ARTHUR NEGRETE
Green Building Final 6/11/2024 Not Ready for Inspection ARTHUR NEGRETE
MERV13>=Final 6/11/2024 Corrections Issued ARTHUR NEGRETE
PLUMBING-Rough 6/11/2024 Approved ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 6/11/2024 SGSOV Not Ready ARTHUR NEGRETE
Smoke Detectors 6/11/2024 Approved ARTHUR NEGRETE
Final 8/23/2024 Not Ready for Inspection ENRIQUE MIRELES
Green Building Final 8/23/2024 Approved ENRIQUE MIRELES
MERV13>=Final 8/23/2024 Not Ready for Inspection ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 8/23/2024 SGSOV Not Ready ENRIQUE MIRELES
Underground Mechanical 8/23/2024 Approved ENRIQUE MIRELES
ELECTRICAL-Final 2/7/2025 Approved ARTHUR NEGRETE
Final 2/7/2025 Partial Approval ARTHUR NEGRETE
HVAC-Final 2/7/2025 Approved ARTHUR NEGRETE
MERV13>=Final 2/7/2025 Approved ARTHUR NEGRETE
PLUMBING-Final 2/7/2025 Approved ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 2/7/2025 SGSOV Approved ARTHUR NEGRETE
Service/Power Release 2/7/2025 Approved ARTHUR NEGRETE
Final 8/5/2025 OK to Issue CofO ARTHUR NEGRETE