6606 W 82ND ST 90045
Certificate Information: 6606 W 82ND ST 90045
- Application / Permit
- 21014-10000-03886
- Plan Check / Job No.
- B21LA14343
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITION TO (E) 1-STORY SFD.
- Permit Issued
- Issued on 12/6/2021
- Issuing Office
- Current Status
- CofO Issued on 7/25/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/6/2021 | DANIEL SANJUAN |
| Corrections Issued | 8/7/2021 | DANIEL SANJUAN |
| Applicant returned to address corrections | 10/8/2021 | LUKE GONZALES |
| Applicant returned to address corrections | 11/3/2021 | RICARDO RAMIREZ |
| Building Plans Picked Up | 11/4/2021 | APPLICANT |
| Plan Check Approved | 12/6/2021 | SAMUEL GONZALEZ |
| Issued | 12/6/2021 | APPLICANT |
| CofO in Progress | 7/18/2022 | HERBERT GIRON |
| Permit Finaled | 7/25/2022 | DANIEL ORRANTE |
| CofO Issued | 7/25/2022 | DANIEL ORRANTE |
| Permit Finaled | 7/25/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 8/30/2021 | ROBERT SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/31/2021 | DINAH GARIN |
| Sewer availability | Cleared | 8/31/2021 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 10/1/2021 | DINAH GARIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Segovia,, Felipe; Lic. No.: C41102 | 2622 DORSET DR TORRANCE, CA 90503 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 1/13/2022 | Corrections Issued | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 1/13/2022 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 1/13/2022 | Approved | BOBBY KEY |
| HVAC-Rough | 1/13/2022 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 1/13/2022 | Corrections Issued | BOBBY KEY |
| Special/Order Compliance | 1/13/2022 | Approved | BOBBY KEY |
| Wood Frame | 1/13/2022 | Not Ready for Inspection | BOBBY KEY |
| ELECTRICAL-Rough | 1/14/2022 | Partial Approval | BOBBY KEY |
| PLUMBING-Rough | 1/14/2022 | Partial Approval | BOBBY KEY |
| Wood Frame | 1/14/2022 | Partial Approval | BOBBY KEY |
| Special/Order Compliance | 2/2/2022 | Conditional Approval | BOBBY KEY |
| Special/Order Compliance | 2/4/2022 | Approved | BOBBY KEY |
| Drywall Nailing | 2/8/2022 | Not Ready for Inspection | BOBBY KEY |
| Green Building Rough | 2/8/2022 | Not Ready for Inspection | BOBBY KEY |
| Wood Frame | 2/8/2022 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 2/9/2022 | Partial Approval | BOBBY KEY |
| Insulation | 2/9/2022 | Partial Approval | BOBBY KEY |
| Drywall Nailing | 2/23/2022 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 2/23/2022 | Not Ready for Inspection | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2022 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 2/23/2022 | Not Ready for Inspection | STEPHANIE SWANSON |
| HVAC-Rough | 2/23/2022 | Corrections Issued | STEPHANIE SWANSON |
| Insulation | 2/23/2022 | Corrections Issued | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 2/25/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Drywall Nailing | 2/25/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 2/25/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Rough | 2/25/2022 | Not Ready for Inspection | JESUS RODRIGUEZ |
| PLUMBING-Rough | 2/25/2022 | Corrections Issued | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 3/1/2022 | Conditional Approval | RYAN SALAZAR |
| Shower Pan | 3/1/2022 | Not Ready for Inspection | RYAN SALAZAR |
| Shower Pan | 4/15/2022 | Approved | KENNETH NAGLE |
| BUILDING-Rough-Frame | 4/20/2022 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 4/20/2022 | Approved | BOBBY KEY |
| HVAC-Rough | 4/20/2022 | Approved | BOBBY KEY |
| PLUMBING-Rough | 4/20/2022 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 4/21/2022 | Approved | BOBBY KEY |
| Drywall Nailing | 4/21/2022 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2022 | Approved | BOBBY KEY |
| Green Building Rough | 4/21/2022 | Approved | BOBBY KEY |
| Insulation | 4/21/2022 | Approved | BOBBY KEY |
| Drywall Nailing | 4/25/2022 | Approved | BOBBY KEY |
| Final | 4/25/2022 | Corrections Issued | BOBBY KEY |
| Interior/Exterior Lathing | 4/27/2022 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 6/30/2022 | Approved | BOBBY KEY |
| Final | 6/30/2022 | Corrections Issued | BOBBY KEY |
| Green Building Final | 6/30/2022 | Approved | BOBBY KEY |
| PLUMBING-Final | 6/30/2022 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 6/30/2022 | SGSOV Not Ready | BOBBY KEY |
| Smoke Detectors | 6/30/2022 | Approved | BOBBY KEY |
| Final | 7/15/2022 | OK to Issue CofO | HERBERT GIRON |
| HVAC-Final | 7/15/2022 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 7/15/2022 | SGSOV Approved | HERBERT GIRON |