321 S BRISTOL AVE 90049

Certificate Information: 321 S BRISTOL AVE 90049

Application / Permit
21014-10000-03879
Plan Check / Job No.
B21LA14273
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Patio Cover
Work Description
detached trellis 1 OF 2
Permit Issued
Issued on 11/19/2021
Issuing Office
Current Status
Permit Finaled on 2/12/2024

Permit Application Status History

Submitted 7/30/2021 APPLICANT
Assigned to Plan Check Engineer 8/19/2021 ARSALAN SHABESTARI
Corrections Issued 8/26/2021 ARSALAN SHABESTARI
Quality Review Completed 9/9/2021 MICHAEL PEREZ
Applicant returned to address corrections 10/28/2021 ARSALAN SHABESTARI
Plan Check Approved 11/9/2021 ARSALAN SHABESTARI
Issued 11/19/2021 APPLICANT
Building Plans Picked Up 11/23/2021 APPLICANT
Permit Finaled 1/30/2024 ARAM AVEDISIAN
CofO in Progress 1/30/2024 ARAM AVEDISIAN
No Progress 2/12/2024 ARAM AVEDISIAN

Permit Application Clearance Information

ZA Case Cleared 9/27/2021 ANNA VIDAL
Eng Process Fee Ord 176,300 Cleared 10/4/2021 RAYMOND MUGAMBWA
Roof/Waste drainage to street Cleared 10/27/2021 RAYMOND MUGAMBWA
Grading Pre-Inspection Cleared 10/28/2021 ARSALAN SHABESTARI

Contact Information

Contractor Shain Development Inc; Lic. No.: 937795-B 832 LAS LOMAS AVE      PACIFIC PALISADES, CA 90272

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/30/2021 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 12/3/2021 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 12/22/2021 Approved JOHN KIDWELL
Footing/Foundation/Slab 12/22/2021 Approved JOHN KIDWELL
Deputy Steel/Welding 1/10/2022 Partial Approval JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 2/8/2022 Approved JOHN KIDWELL
Footing/Foundation/Slab 2/8/2022 Approved JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 2/28/2022 Corrections Issued KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 3/3/2022 Partial Approval OGANES TARAKHCHYAN
Interior/Exterior Lathing 3/16/2022 Partial Approval JUAN VALENZUELA
Insulation 3/24/2022 Approved JUAN VALENZUELA
Special/Order Compliance 4/21/2022 Partial Inspection STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 5/20/2022 Approved JOHN KIDWELL
Footing/Foundation/Slab 5/20/2022 Corrections Issued JOHN KIDWELL
ELECTRICAL-Rough 10/20/2022 Partial Approval KEVIN SARGSYAN
Insulation 11/2/2022 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 12/19/2022 Partial Approval ASHLEY THOMPSON
BUILDING-Rough-Frame 4/11/2023 Approved OGANES TARAKHCHYAN
Final 4/11/2023 Corrections Issued OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 4/11/2023 SGSOV Not Ready OGANES TARAKHCHYAN
Smoke Detectors 4/11/2023 Approved OGANES TARAKHCHYAN
Final 12/7/2023 Not Ready for Inspection ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 12/7/2023 SGSOV Not Required ARAM AVEDISIAN
Final 12/14/2023 Corrections Issued ARAM AVEDISIAN
Final 1/30/2024 Permit Finaled ARAM AVEDISIAN