1627 W 35TH ST 90018

Certificate Information: 1627 W 35TH ST 90018

Application / Permit
21014-10000-03878
Plan Check / Job No.
B21LA14272
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION AND CONVERSION OF EXISTING GARAGE TO NEW ADU PER LAMC 12.22 A.33(c) and (d) AND WFPP
Permit Issued
Issued on 8/18/2022
Issuing Office
Metro
Current Status
CofO Issued on 9/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/30/2021 APPLICANT
Assigned to Plan Check Engineer 8/5/2021 SAMUEL GONZALEZ
Corrections Issued 8/7/2021 SAMUEL GONZALEZ
Applicant returned to address corrections 7/8/2022 JASON JANGADA
Plan Check Approved 7/14/2022 JASON JANGADA
Building Plans Picked Up 8/5/2022 APPLICANT
Issued 8/18/2022 APPLICANT
CofO in Progress 7/7/2023 SABAS ALONSO
Permit Finaled 9/5/2023 DEROLD HAUFF
CofO Issued 9/5/2023 DEROLD HAUFF
Permit Finaled 9/5/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/4/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 10/6/2021 WALLIE JONG
Sewer availability Cleared 10/6/2021 WALLIE JONG
Construction near power lines Cleared 2/15/2022 RIDWAN HARDY
Hydrant and Access approval Cleared 4/1/2022 DWAYNE LAURENT
Low Impact Development Cleared 4/14/2022 KHAING AYE
Roof/Waste drainage to street Cleared 5/9/2022 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/26/2022 Approved SABAS ALONSO
Footing/Foundation/Slab 9/26/2022 Approved SABAS ALONSO
METHANE-Barrier 9/26/2022 Approved SABAS ALONSO
METHANE-Subgrade 9/26/2022 Approved SABAS ALONSO
BUILDING-Rough-Frame 10/27/2022 Partial Approval SABAS ALONSO
Underground Mechanical 10/27/2022 Partial Approval SABAS ALONSO
Insulation 11/2/2022 Partial Approval SABAS ALONSO
BUILDING-Rough-Frame 12/22/2022 Not Ready for Inspection SABAS ALONSO
ELECTRICAL-Rough 12/22/2022 Approved SABAS ALONSO
Green Building Rough 12/22/2022 Not Ready for Inspection SABAS ALONSO
METHANE-Rough 12/22/2022 Approved SABAS ALONSO
PLUMBING-Rough 12/22/2022 Approved SABAS ALONSO
BUILDING-Rough-Frame 12/28/2022 Approved SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 12/28/2022 Partial Approval SABAS ALONSO
Green Building Rough 12/28/2022 Approved SABAS ALONSO
HVAC-Rough 12/28/2022 Approved SABAS ALONSO
METHANE-Rough 12/28/2022 Approved SABAS ALONSO
Insulation 1/10/2023 Approved LILIANA PORTILLO
Underground Mechanical 1/10/2023 Partial Approval LILIANA PORTILLO
Interior/Exterior Lathing 1/24/2023 Partial Approval SABAS ALONSO
Sewer 1/24/2023 Approved SABAS ALONSO
Drywall Nailing 2/13/2023 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 2/13/2023 Partial Approval ALEJANDRO DE ARTOLA
ELECTRICAL-Final 6/14/2023 Approved SABAS ALONSO
Final 6/14/2023 Corrections Issued SABAS ALONSO
Gas Test 6/14/2023 Approved SABAS ALONSO
Green Building Final 6/14/2023 Corrections Issued SABAS ALONSO
Rough-Elec/Plmb/HVAC 6/14/2023 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 6/14/2023 SGSOV Not Ready SABAS ALONSO
Smoke Detectors 6/14/2023 Approved SABAS ALONSO
Final 7/6/2023 OK to Issue CofO SABAS ALONSO
Green Building Final 7/6/2023 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 7/6/2023 SGSOV Approved SABAS ALONSO