1627 W 35TH ST 90018
Certificate Information: 1627 W 35TH ST 90018
- Application / Permit
- 21014-10000-03878
- Plan Check / Job No.
- B21LA14272
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION AND CONVERSION OF EXISTING GARAGE TO NEW ADU PER LAMC 12.22 A.33(c) and (d) AND WFPP
- Permit Issued
- Issued on 8/18/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/5/2021 | SAMUEL GONZALEZ |
| Corrections Issued | 8/7/2021 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 7/8/2022 | JASON JANGADA |
| Plan Check Approved | 7/14/2022 | JASON JANGADA |
| Building Plans Picked Up | 8/5/2022 | APPLICANT |
| Issued | 8/18/2022 | APPLICANT |
| CofO in Progress | 7/7/2023 | SABAS ALONSO |
| Permit Finaled | 9/5/2023 | DEROLD HAUFF |
| CofO Issued | 9/5/2023 | DEROLD HAUFF |
| Permit Finaled | 9/5/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/4/2021 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 10/6/2021 | WALLIE JONG |
| Sewer availability | Cleared | 10/6/2021 | WALLIE JONG |
| Construction near power lines | Cleared | 2/15/2022 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 4/1/2022 | DWAYNE LAURENT |
| Low Impact Development | Cleared | 4/14/2022 | KHAING AYE |
| Roof/Waste drainage to street | Cleared | 5/9/2022 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/26/2022 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 9/26/2022 | Approved | SABAS ALONSO |
| METHANE-Barrier | 9/26/2022 | Approved | SABAS ALONSO |
| METHANE-Subgrade | 9/26/2022 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 10/27/2022 | Partial Approval | SABAS ALONSO |
| Underground Mechanical | 10/27/2022 | Partial Approval | SABAS ALONSO |
| Insulation | 11/2/2022 | Partial Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 12/22/2022 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 12/22/2022 | Approved | SABAS ALONSO |
| Green Building Rough | 12/22/2022 | Not Ready for Inspection | SABAS ALONSO |
| METHANE-Rough | 12/22/2022 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 12/22/2022 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 12/28/2022 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/28/2022 | Partial Approval | SABAS ALONSO |
| Green Building Rough | 12/28/2022 | Approved | SABAS ALONSO |
| HVAC-Rough | 12/28/2022 | Approved | SABAS ALONSO |
| METHANE-Rough | 12/28/2022 | Approved | SABAS ALONSO |
| Insulation | 1/10/2023 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 1/10/2023 | Partial Approval | LILIANA PORTILLO |
| Interior/Exterior Lathing | 1/24/2023 | Partial Approval | SABAS ALONSO |
| Sewer | 1/24/2023 | Approved | SABAS ALONSO |
| Drywall Nailing | 2/13/2023 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 2/13/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 6/14/2023 | Approved | SABAS ALONSO |
| Final | 6/14/2023 | Corrections Issued | SABAS ALONSO |
| Gas Test | 6/14/2023 | Approved | SABAS ALONSO |
| Green Building Final | 6/14/2023 | Corrections Issued | SABAS ALONSO |
| Rough-Elec/Plmb/HVAC | 6/14/2023 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 6/14/2023 | SGSOV Not Ready | SABAS ALONSO |
| Smoke Detectors | 6/14/2023 | Approved | SABAS ALONSO |
| Final | 7/6/2023 | OK to Issue CofO | SABAS ALONSO |
| Green Building Final | 7/6/2023 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 7/6/2023 | SGSOV Approved | SABAS ALONSO |