1340 S TREMAINE AVE 90005

Certificate Information: 1340 S TREMAINE AVE 90005

Application / Permit
21014-10000-03872
Plan Check / Job No.
B21LA14259
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD TO AN EXISTING DETACHED 1-CAR GARAGE AND CONVERT INTO AN ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33 (c) AND (d).
Permit Issued
Issued on 6/7/2022
Issuing Office
Metro
Current Status
CofO Issued on 5/16/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/5/2021 APPLICANT
Assigned to Plan Check Engineer 8/10/2021 STANLEY RAAP
Corrections Issued 8/10/2021 STANLEY RAAP
Applicant returned to address corrections 5/11/2022 CRISTINA SALAZAR
Plan Check Approved 5/20/2022 DANIEL SANJUAN
Issued 6/7/2022 APPLICANT
CofO in Progress 5/15/2023 CALEB MEISTER
CofO in Progress 5/15/2023 CALEB MEISTER
Permit Finaled 5/16/2023 DEROLD HAUFF
CofO Issued 5/16/2023 DEROLD HAUFF
Permit Finaled 5/16/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/26/2021 WALLIE JONG
Roof/Waste drainage to street Cleared 8/26/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 8/30/2021 WALLIE JONG
Sewer availability Cleared 8/30/2021 WALLIE JONG
CPC Cleared 10/5/2021 TERRI OSBORNE
CPC Cleared 10/5/2021 TERRI OSBORNE
Construction near power lines Cleared 10/30/2021 RIDWAN HARDY
Low Impact Development Cleared 1/7/2022 TA ANH

Contact Information

Contractor Owner-Builder       ,
Engineer Alson,, Ken; Lic. No.: C41697 9744 MAPLE ST 201      BELLFLOWER, CA 90706

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Barrier 8/5/2022 Approved STUART CHAPMAN
METHANE-Subgrade 8/5/2022 Approved STUART CHAPMAN
Pre-Inspection 8/5/2022 Approved STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 8/23/2022 Partial Approval STUART CHAPMAN
PLUMBING-Rough 8/23/2022 Partial Approval STUART CHAPMAN
Sewer 8/23/2022 Approved STUART CHAPMAN
Underground Mechanical 8/23/2022 Partial Approval STUART CHAPMAN
Excavation/Setback/Form/Re-Bar 9/8/2022 Approved JOSE AVILA
BUILDING-Rough-Frame 10/28/2022 Corrections Issued STUART CHAPMAN
ELECTRICAL-Rough 10/28/2022 Approved STUART CHAPMAN
Green Building Rough 10/28/2022 Not Ready for Inspection STUART CHAPMAN
HVAC-Rough 10/28/2022 Approved STUART CHAPMAN
METHANE-Rough 10/28/2022 Approved STUART CHAPMAN
PLUMBING-Rough 10/28/2022 Approved STUART CHAPMAN
Wood Frame 10/28/2022 Not Ready for Inspection STUART CHAPMAN
Deputy Drilled-In Anchors 11/2/2022 Conditional Approval STUART CHAPMAN
Deputy Wood Construction 11/2/2022 Conditional Approval STUART CHAPMAN
Deputy Wood Construction 11/3/2022 Conditional Approval STUART CHAPMAN
BUILDING-Rough-Frame 11/4/2022 Approved STUART CHAPMAN
Green Building Rough 11/4/2022 Not Ready for Inspection STUART CHAPMAN
Green Building Rough 11/16/2022 Approved STUART CHAPMAN
Insulation 11/16/2022 Approved STUART CHAPMAN
Interior/Exterior Lathing 11/16/2022 Partial Approval STUART CHAPMAN
Drywall Nailing 11/23/2022 Approved BRENDAN MORELLI
Underground Mechanical 12/28/2022 Partial Approval THOMAS LOGRASSO
ELECTRICAL-Final 2/7/2023 Approved CALEB MEISTER
Service/Power Release 2/7/2023 Not Ready for Inspection CALEB MEISTER
Final 2/10/2023 Not Ready for Inspection CALEB MEISTER
Footing/Foundation/Slab 2/10/2023 Approved CALEB MEISTER
Green Building Final 2/10/2023 Not Ready for Inspection CALEB MEISTER
SGSOV-Seismic Gas S/O Valve 2/10/2023 SGSOV Approved CALEB MEISTER
Smoke Detectors 2/10/2023 Approved CALEB MEISTER
Final 4/12/2023 Conditional Approval CALEB MEISTER
Green Building Final 4/12/2023 Approved CALEB MEISTER
HVAC-Final 4/12/2023 Approved CALEB MEISTER
PLUMBING-Final 4/12/2023 Approved CALEB MEISTER
Service/Power Release 4/12/2023 Approved CALEB MEISTER
Final 5/15/2023 OK to Issue CofO CALEB MEISTER