2129 W ADDISON WAY 90041
Certificate Information: 2129 W ADDISON WAY 90041
- Application / Permit
- 21014-10000-03862
- Plan Check / Job No.
- B21LA14230
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN. CONVERT (E) DETACHED GARAGE WITH NEW ADDITION TO ACCESSORY DWELLING UNIT AND STORAGE PER LAMC 12.22 A.33 (c)-(d).
- Permit Issued
- Issued on 10/11/2021
- Issuing Office
- Current Status
- Issued on 10/11/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 7/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 8/2/2021 | KEVIN MORALES |
| Corrections Issued | 8/2/2021 | KEVIN MORALES |
| Plan Check Approved | 9/22/2021 | KEVIN MORALES |
| Issued | 10/11/2021 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 8/6/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 8/6/2021 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 8/6/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 8/6/2021 | RENZ SORIANO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lee,, Richard C C; Lic. No.: S1371 | 19321 VANOWEN ST RESEDA, CA 91335 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/14/2022 | Partial Approval | CRAIG VAUGHAN |
| Deputy Drilled-In Anchors | 3/16/2022 | Conditional Approval | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 3/17/2022 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 3/17/2022 | Approved | STUART CHAPMAN |
| METHANE-Barrier | 3/17/2022 | Approved | STUART CHAPMAN |
| METHANE-Subgrade | 3/17/2022 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2022 | Partial Approval | CRAIG VAUGHAN |
| Rough-Elec/Plmb/HVAC | 5/3/2022 | Corrections Issued | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 8/17/2022 | Corrections Issued | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 8/23/2022 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 8/23/2022 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2022 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 8/23/2022 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 8/23/2022 | Approved | CRAIG VAUGHAN |
| METHANE-Rough | 8/23/2022 | Approved | CRAIG VAUGHAN |
| Insulation | 9/2/2022 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 10/20/2022 | Approved | CRAIG VAUGHAN |
| Underground Mechanical | 10/20/2022 | Partial Approval | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 10/27/2022 | Approved | CHARLES BOGHOSKHAN |
| Shower Pan | 10/27/2022 | Approved | CHARLES BOGHOSKHAN |
| Pre-Inspection | 12/1/2022 | Approved | CRAIG VAUGHAN |
| Underground Mechanical | 12/1/2022 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 5/18/2023 | Corrections Issued | CRAIG VAUGHAN |
| Final | 5/18/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Green Building Final | 5/18/2023 | Approved | CRAIG VAUGHAN |
| HVAC-Final | 5/18/2023 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 5/18/2023 | Corrections Issued | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 5/18/2023 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 5/18/2023 | Approved | CRAIG VAUGHAN |